To zoom, hold down the Shift key and drag a rectangle.
|
|
Location Information | Location Notes |
---|---|
Existing Spooner Lake State Park developed area.
|
National Park Service (NPS) | None | |||
Nevada Tahoe Resource Team (NTRT) | Kevin Fromherz - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Kevin Fromherz - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | Cassandra Hughes - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
Tahoe Fund (Tahoe Fund) | Amy Berry - Tahoe Fund (Tahoe Fund) | |||
U.S. Federal Highway Administration (FHWA) | Matt Ambroziak - U.S. Department of Transportation (US DOT) |
Miles of Trails Developed or Improved | None | miles | |
Facilities Improved or Created | None | number |
Educational and Interpretive Programs Produced | |||||||
---|---|---|---|---|---|---|---|
|
2021 | 2022 | 2023 | Total | Units | ||
Primary EIP Program | Program Objective | Program Status | |||||
Sustainable Recreation | Education and Interpretation | Delivered | 8 | 8 | number | ||
Total | 0 | 0 | 8 | 8 | number |
Facilities Improved or Created | |||||||
---|---|---|---|---|---|---|---|
|
2021 | 2022 | 2023 | Total | Units | ||
Action Performed | Primary Facility Type | Primary Purpose of Facility | |||||
Created | Buildings & Grounds | Recreation | 0 | 2 | 2 | number | |
Total | 0 | 2 | 0 | 2 | number |
Total | |||
---|---|---|---|
Lake Tahoe License Plate Program (NDSL) | $45,000 | $45,000 | $0 |
Land and Water Conservation Fund (NPS) | $593,533 | $593,533 | $0 |
Nevada State Parks (NV State Parks) | $363,073 | $363,073 | $0 |
Recreational Trails Program Funds (FHWA) | $90,000 | $90,000 | $0 |
Tahoe Bonds Act (NDSL) | $2,902,181 | $2,902,181 | $0 |
Tahoe Fund (Tahoe Fund) | $300,000 | $300,000 | $0 |
Grand Total | $4,293,787 | $4,293,787 | $0 |
Total | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | |
---|---|---|---|---|---|---|---|---|---|---|
Land and Water Conservation Fund | $593,534 | $0 | $549,275 | $44,259 | $0 | $0 | $0 | $0 | $0 | $0 |
Nevada State Parks | $4,038 | $0 | $3,121 | $0 | $917 | $0 | $0 | $0 | $0 | $0 |
Recreational Trails Program Funds | $84,598 | $60,972 | $23,626 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Tahoe Bonds Act | $4,182,883 | $46,699 | $45,909 | $2,719,239 | $938,099 | $96,922 | $255,035 | $80,980 | $0 | $0 |
Tahoe Fund | $171,229 | $0 | $171,229 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $5,036,282 | $107,671 | $793,160 | $2,763,498 | $939,016 | $96,922 | $255,035 | $80,980 | $0 | $0 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
01/08/2024 4:40 PM | Kevin Fromherz | Project is complete as of this year, some warranty work and punch list items were covered this year but had been paid out of prior years. This years accomplishments included the installation of the interpretive panels at the visitor center. | ||
03/28/2023 3:21 PM | Beth Vollmer | Improvements in 2022 include a new visitor center and amphitheater. The Spooner Lake Visitor Center and Amphitheater is a hub of information for the Spooner Lake and Backcountry State Park. The project includes: new restroom facilities, convenience room with planned vending machines, a warming hut, audio/video and Wi-Fi/device charging, interpretive pavilion with map and way finding features, gift shop and information counter, amphitheater, and park office. The site has also been improved with new landscaping, irrigation, and trail side amenities, and a pathway system that links into existing trails. |
||
01/17/2023 4:27 PM | Kevin Fromherz | Remaining projects should be completed in Summer of 2023. | ||
12/17/2021 2:06 PM | Jay Howard | Expenditure update for 2021 is based on invoices through November 2021 (construction and consultant assistance). | ||
09/03/2021 2:34 PM | Jay Howard | Current expenditures are up to 09/03/2021. It is estimated that up to 1/2 million of project budget for phase 1 will be left over. All excess Phase 1 project monies will roll over into Phase 2 of this project. The estimated project shortfall for Phase 2 is 3 million. | ||
01/12/2021 5:23 PM | Jay Howard | Current expenditures are up to the end of 2020, and include further design costs for the overall Spooner Frontcountry Improvements design, and early construction costs (permitting and bidding). 1st bid did not result in the selection of a contractor. 2nd bid will occur in Jan/Feb 2021. | ||
01/23/2020 9:24 AM | Jay Howard | Current expenditures are reported up to the end of 2019. Construction will begin in spring of 2020, and last for two construction seasons (Oct 2021). Additional planned funding: Tahoe Fund - $300,000; RTP - $90,000; LWCF - $500,000. Leftover project funding will go toward phase 2 design and construction. |