Basics
The Community Service Area (CSA) # 5 Erosion Control Project includes the developed portions of the Tahoe Cedars subdivision southwest of Highway 89 between the El Dorado County Line and Poplar Street. The goal of the Project is to reduce the concentration of fine sediment in the storm water which exits the Project area before reaching Lake Tahoe. The Project was split into multiple phases. The final phase (Phase 3) project area is bounded by Placer Street to the east, Oak Street to the south, and the Placer/El Dorado County line to the north and west. Construction of phase 3 is estimated to occur in 2022.

Post-Implementation
2011
2014
2018
$1,577,886

Dan Kikkert (dan.kikkert@edcgov.us)
06/01/2014
12/22/2020