Continue pedestrian sidewalks, lighting, transit stops, and class II bike lanes from the limits of the completed Phase 1 project (Larch Avenue) to the western limits of Ski Run Boulevard (+.45 Center line Miles).

Planning/Design
2017
2024
2024
$6,149,000

Stan Hill (shill@cityofslt.us)
10/17/2016
03/11/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes
Pioneer Trail, Limits of Larch Avenue to Ski Run Blvd.

Organizations

EIP Details

EIP Basics

03.02.02.0078 - Pioneer Trail Pedestrian Project - Phase II

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2024 2023 2022 2021 2020 2019 2018 2017
California Active Transportation Program (ATP) Funds - State (Caltrans) $1,200,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $1,200,000 $1,200,000 $0 $0 $0 $0 $0 $0 $0
California Highway Infrastructure Program (HIP) (FHWA) $111,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $111,000 $0 $111,000 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0
City of South Lake Tahoe General Fund (CSLT) $2,045,431
Preliminary Engineering $54,415 $0 $0 $0 $0 $0 $0 $54,415 $0
Right of Way (aka Land Acquisition) $53,250 $0 $53,250 $0 $0 $0 $0 $0 $0
Construction $1,937,766 $1,937,766 $0 $0 $0 $0 $0 $0 $0
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) $1,850,775
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $299,775 $0 $299,775 $0 $0 $0 $0 $0 $0
Construction $1,551,000 $1,551,000 $0 $0 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $1,025,688
Preliminary Engineering $420,000 $0 $0 $0 $0 $0 $0 $420,000 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $605,688 $605,688 $0 $0 $0 $0 $0 $0 $0
Grand Total $6,232,894 $5,294,454 $464,025 $0 $0 $0 $0 $474,415 $0

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Pedestrian and Bicycle Routes Improved or Constructed [Action Performed: Constructed], [Path or Route Type: Class II/Bike Lane] 0.92 miles
Miles of Pedestrian and Bicycle Routes Improved or Constructed [Action Performed: Constructed], [Path or Route Type: Sidewalk] 0.92 miles

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$6,149,000
$6,232,894
($83,894)

Total
California Active Transportation Program (ATP) Funds - State (Caltrans) $1,200,000 $1,200,000 $0
California Highway Infrastructure Program (HIP) (FHWA) $111,000 $111,000 $0
City of South Lake Tahoe General Fund (CSLT) $2,045,431 $2,045,431 $0
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) $1,850,775 $1,850,775 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $1,025,688 $1,025,688 $0
Grand Total $6,232,894 $6,232,894 $0

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018 2017
California Active Transportation Program (ATP) Fun... $0 $0 $0 $0 $0 $0 $0 $0
California Highway Infrastructure Program (HIP) $3,326 $670 $2,656 $0 $0 $0 $0 $0
City of South Lake Tahoe General Fund $47,659 $8,063 $478 $11,518 $19,005 $8,595 $0 $0
Congestion Mitigation and Air Quality Program (CMA... $0 $0 $0 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - Califo... $361,178 $58,219 $1,034 $88,897 $146,690 $66,338 $0 $0
Grand Total $412,163 $66,952 $4,168 $100,415 $165,695 $74,933 $0 $0

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
01/05/2023 11:56 AM Randy Carlson City has retained a right of way specialist and is beginning to acquire easements and right to enter contracts.
01/03/2022 4:39 PM Randy Carlson 60% design plans currently being finalized. The City expects to solicit a right of way specialist to assist with property acquisitions within the next few months.
05/24/2018 9:23 AM Jim Marino Jim Marino - May 2018 - City Engineering staff will be releasing planning and design RFP in June 2018. Additionally, staff has begun Caltrans RFA for PE phase.
10/18/2016 9:48 AM Karen Fink This project was stuck in the "proposed" queue and didn't make it onto the original list of projects downloaded by Stantec for the corridor list. Karen added it to the South Tahoe Gauntlet corridor on 10/18/16.