Overview

Basics

Basics
The Project site is along Apache Avenue from the US 50/ SR 89 intersection to the Lake Tahoe Environmental Science Magnet School and proposes to implement sustainable mobility improvements to provide a safe walkable and bikeable roadway. The project will result in reconstructing approximately 0.39 miles of Apache Avenue with the addition of curb and gutter, a stormwater drainage system, a Class 1 shared use path, a sidewalk, and updating existing Class 2 bike lanes on the northbound and southbound sides. Proposed safety improvements include increased signage and a driver speed feebdback sign, high visibility crosswalks and pavement markings, and ADA curb ramps.

Planning/Design
2020
2024
2026
$4,058,000

Dan Kikkert (dan.kikkert@edcgov.us)
12/21/2016
02/07/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.02.02.0006 - Apache Avenue Pedestrian Safety and Connectivity Project

This project is on the EIP 5-year list.

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2026 2025 2024 2023 2022 2021 2020 2019
AQ Mitigation Funds (TRPA) $29,000
Preliminary Engineering $29,000 $0 $0 $0 $0 $0 $0 $29,000 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0
California Active Transportation Program (ATP) Funds - Federalized (Caltrans) $1,701,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $1,701,000 $0 $0 $1,701,000 $0 $0 $0 $0 $0
Carbon Reduction Program - California (FHWA) $545,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $545,000 $0 $0 $545,000 $0 $0 $0 $0 $0
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) $499,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $499,000 $0 $0 $499,000 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $1,000,000
Preliminary Engineering $500,000 $0 $0 $0 $0 $0 $0 $500,000 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $500,000 $0 $0 $500,000 $0 $0 $0 $0 $0
WQ Mitigation Funds (TRPA) $284,000
Preliminary Engineering $35,780 $0 $0 $0 $0 $0 $0 $35,780 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $248,220 $0 $0 $183,440 $0 $64,780 $0 $0 $0
Grand Total $4,058,000 $0 $0 $3,428,440 $0 $64,780 $0 $564,780 $0

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$4,058,000
$4,058,000
$0

Total
AQ Mitigation Funds (TRPA) $29,000 $29,000 $0
California Active Transportation Program (ATP) Funds - Federalized (Caltrans) $1,701,000 $1,701,000 $0
Carbon Reduction Program - California (FHWA) $545,000 $545,000 $0
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) $499,000 $499,000 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $1,000,000 $1,000,000 $0
WQ Mitigation Funds (TRPA) $284,000 $284,000 $0
Grand Total $4,058,000 $4,058,000 $0

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020
AQ Mitigation Funds $29,000 $0 $15,442 $13,558 $0
California Active Transportation Program (ATP) Fun... $362,060 $362,060 $0 $0 $0
Carbon Reduction Program - California $400,000 $400,000 $0 $0 $0
Surface Transportation Block Grant (STBG) - Califo... $453,000 $135,000 $233,353 $84,647 $0
WQ Mitigation Funds $145,205 $128,000 $17,205 $0 $0
Grand Total $1,389,265 $1,025,060 $266,000 $98,205 $0

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

Notes

Notes
01/27/2023 4:54 PM Dan Kikkert Key Points:
- The project will help support the Walk to School Day, Bike to School Day, and other activities in cooperation with the school district and the Meyers community.
- Apache Avenue is a major collector and provides challenges faced by the community walking and bicycling to the school and the nearby Tahoe Paradise Park.
- The project is within one of the high priority watersheds for pollutant load delivery to Lake Tahoe with planned improvements reducing fine sediment from stormwater runoff.
07/19/2022 2:09 PM Donaldo Palaroan CMAQ $1,468M transferred to San Bernardino Class 1 (#03.02.02.0027)
06/14/2022 5:09 PM Judy Weber CMAQ $1,468M transferred from Meyers Corridor Improvement project
08/19/2020 10:41 AM Dan Kikkert The project to include construction of water quality improvements.
01/31/2019 9:42 AM Dan Kikkert Project includes the establishment of an Underground Utility District (UUD) on Apache between Highway 50 and San Bernardino in preparation of project improvements.
10/18/2016 10:40 AM Karen Fink Morgan says about this project: This is ped activated beacon, new crosswalk, sidewalks, roadway reconfiguration, and class1 path.