Location Information | Location Notes |
---|---|
|
Douglas County, NV (DGCO) | Courtney Walker - Douglas County, NV (DGCO) | |||
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Kevin Fromherz - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
No expected performance measures set for this project.
No annual performance measure accomplishments entered for this project.
No accomplishments to report for: | |
Year(s) | 2010, 2011, 2012, 2013, 2014 |
---|---|
Explanation | Project was to provide stormwater infrastructure for larger-scale development; development did not go through. |
Total | |||
---|---|---|---|
Unknown or Unassigned | $1,925,472 | $1,925,472 | $0 |
Grand Total | $1,925,472 | $1,925,472 | $0 |
Total | 2013 | 2012 | 2011 | 2010 | |
---|---|---|---|---|---|
Southern Nevada Public Land Management Act | $1,010,569 | $175,368 | $181,293 | $501,810 | $152,098 |
Tahoe Bonds Act | $914,903 | $199,222 | $181,293 | $531,062 | $3,326 |
Grand Total | $1,925,472 | $374,590 | $362,586 | $1,032,872 | $155,424 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
05/21/2014 6:02 PM | System | Project substantially complete in 2012 but some expenditures still to occur in 2013. | ||
05/21/2014 6:01 PM | System | The PM of 1 mile of roadway treated was reported last year (so should not be duplicated). |