Forest Restoration IV includes the Sand Harbor SNPLMA Round 11 HFR, Tunnel Creek SNPLMA Round 11 HFR, matching funds (Tahoe Bond) for the Slaughterhouse Round 11 HFR, matching funds (Tahoe Bond) for Tunnel Creek Round 9, North Canyon Road fuel break, Aspen restoration, Sand Harbor South, Ridgetop cable demo and Spooner LR. Treatment includes hand thinning, reducing down woody material, pile burning, underburning, chipping and biomass removal. To evaluate the state of wildlife populations in treated areas, seasonal survey and monitoring work is completed. These surveys are used to inform future forest restoration efforts, as well as evaluate the effects of past efforts.

Completed
2012
2012
2017
$966,802

Anna Higgins (ahiggins@forestry.nv.gov)
06/01/2014
01/14/2019
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

02.01.01.0014 - Forest Restoration IV - Nevada

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Acres of SEZ Restored or Enhanced
2012 2013 2014 2015 2016 2017 Total Units
Action Performed
Enhanced 3 3 acres
Total 3 0 0 0 0 0 3 acres
Acres of Habitat Protected
2012 2013 2014 2015 2016 2017 Total Units
EIP Focal Species Habitat Type
Aspen (Populus tremuloides) Aspen 74 74 acres
Total 0 0 74 0 0 0 74 acres
Acres of Habitat Restored or Enhanced
2012 2013 2014 2015 2016 2017 Total Units
Action Performed Habitat Type
Restored Aspen 74 27 13 2 116 acres
Restored Forested Upland 106 93 150 52 401 acres
Restored Late-Seral/Old Growth 24 24 acres
Total 0 0 204 120 163 54 541 acres
Acres of Forest Fuels Reduction Treatment
2012 2013 2014 2015 2016 2017 Total Units
Initial or Maintenance Treatment Property Ownership Treatment Type Treatment Zone
Initial Nevada State Parks Hand Thinning Community Defense Zone 5 43 42 90 acres
Initial Nevada State Parks Hand Thinning General Forest 123 123 acres
Initial Nevada State Parks Hand Thinning Threat Zone 100 68 14 10 192 acres
Initial Nevada State Parks Mechanical Thinning Threat Zone 5 5 10 acres
Initial Nevada State Parks Prescribed Burning Community Defense Zone 28 27 23 32 28 138 acres
Initial Nevada State Parks Prescribed Burning Threat Zone 10 173 76 88 347 acres
Maintenance Nevada State Parks Chipping Community Defense Zone 9 9 acres
Maintenance Nevada State Parks Chipping Threat Zone 37 37 acres
Maintenance Nevada State Parks Hand Thinning Community Defense Zone 25 25 acres
Total 48 200 204 231 190 98 971 acres

Funding

Expected Funding

Expected Funding
$966,802
$966,802
$0

Total
Southern Nevada Public Land Management Act (BLM) $135,746 $135,746 $0
Tahoe Bonds Act (NDSL) $831,056 $831,056 $0
Grand Total $966,802 $966,802 $0

Reported Expenditures

Reported Expenditures
Total 2017 2016 2015 2014 2013 2012
Southern Nevada Public Land Management Act $135,746 $12,736 $14,771 $85,208 $23,031 $0 $0
Tahoe Bonds Act $831,056 $120,259 $186,237 $120,375 $198,704 $179,712 $25,769
Grand Total $966,802 $132,995 $201,008 $205,583 $221,735 $179,712 $25,769

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
12/13/2018 11:07 AM Roland Shaw Tunnel Creek Round 11 project was terminated at 15% complete and remaining funds returned to BLM. Shared use bikeway construction made it too difficult to access.