Overview

Basics

Basics
Development of an updated General Management Plan to guide capital improvements and management in Lake Tahoe Nevada State Park. Project may include monitoring use patterns and use surveys.

Deferred
2011
2011
2017
$250,000

Kevin Fromherz (kfromherz@parks.nv.gov)
06/01/2014
01/20/2016
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.01.02.0014 - Lake Tahoe Nevada State Park General Management Plan Update

Performance Measures

Expected Performance Measures

Expected Performance Measures
Facilities Improved or Created None number

Reported Performance Measures

Reported Performance Measures

No annual performance measure accomplishments entered for this project.

Funding

Expected Funding

Expected Funding
$250,000
$200,228
$49,772

Total
Unknown or Unassigned $200,228 $200,228 $0
Grand Total $200,228 $200,228 $0

Reported Expenditures

Reported Expenditures
Total 2017 2016 2015 2014 2013 2012 2011
Tahoe Bonds Act $185,528 $0 $0 $0 $0 $0 $158,276 $27,252
Grand Total $185,528 $0 $0 $0 $0 $0 $158,276 $27,252

Photos

Photos

No photos available.

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
02/06/2015 9:47 AM Elizabeth Kingsland Consultant contract work was completed. Additional work to complete remaining components of the General Management Plan will be completed by Nevada State Park staff.
05/21/2014 6:02 PM System 40% complete, anticipated draft in September 2012, completion 12/31/12
05/21/2014 6:01 PM System Consultant anticipated to begin work July 2011.