Overview

Basics

Basics
Retrofit and/or provide water quality BMP-compliant day use parking for resort guests and employees. Reconfigure and retrofit road and day use parking, including implementation of water quality BMPs. Retrofit Village area to provide improved circulation efficiency and safety and implement water quality protection BMPs. Reconfigure campground entrance and primary circulation within the southern campground area.

Implementation
2015
2016
2027
$6,500,000

Brian Garrett (brian.garrett@usda.gov)
11/18/2014
10/19/2023
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

01.01.01.0124 - Camp Richardson Resort & Campground BMPs & Retrofit

This project is on the EIP 5-year list.

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2027 2026 2025 2024 2023 2022 2021 2020 2019 2018 2017 2016 2015
Private (Business) (Private) $29,151
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $29,151 $0 $0 $0 $0 $0 $0 $0 $29,151 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $225,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $225,000 $0 $0 $0 $0 $0 $0 $0 $225,000 $0 $0 $0 $0 $0
Grand Total $254,151 $0 $0 $0 $0 $0 $0 $0 $254,151 $0 $0 $0 $0 $0

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Roads Decommissioned or Retrofitted None miles
Facilities Improved or Created None number

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2016 2017 2019 2020 2021 2022 Total Units
Property Ownership Road Type Treatment Type
U.S. Forest Service Paved Retrofitted 1.5 0 0 0 0.5 2 miles
Total 0 1.5 0 0 0 0.5 2 miles
Miles of Pedestrian and Bicycle Routes Improved or Constructed
2016 2017 2019 2020 2021 2022 Total Units
Action Performed Path or Route Type
Constructed Class I/Shared Use Path 0.5 0.5 miles
Total 0 0 0 0 0 0.5 0.5 miles
Facilities Improved or Created
2016 2017 2019 2020 2021 2022 Total Units
Action Performed Primary Facility Type Primary Purpose of Facility
Improved Buildings & Grounds Recreation 1 1 1 0 3 number
Total 0 0 1 1 1 0 3 number
Forest Upland Facilities Retrofitted for Stormwater
2016 2017 2019 2020 2021 2022 Total Units
Ownership Type of Retrofit Action
USFS Lake Tahoe Basin Management Unit Retrofitted 3 3 number
Total 3 0 0 0 0 0 3 number

No accomplishments to report for:
Year(s) 2018
Explanation No projects to report

Funding

Expected Funding

Expected Funding
$6,500,000
$6,250,000
$250,000

Total
Private (Business) (Private) $25,000 $25,000 $0
Southern Nevada Public Land Management Act (USFS - LTBMU) $2,000,000 $2,000,000 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $225,000 $225,000 $0
U.S. Forest Service (USFS - LTBMU) $4,000,000 $4,000,000 $0
Grand Total $6,250,000 $6,250,000 $0

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018 2017 2016 2015
Southern Nevada Public Land Management Act $1,680,000 $0 $0 $0 $0 $0 $0 $680,000 $1,000,000 $0
Surface Transportation Block Grant (STBG) - Califo... $225,000 $0 $225,000 $0 $0 $0 $0 $0 $0 $0
U.S. Forest Service $2,377,000 $0 $539,000 $300,000 $100,000 $200,000 $400,000 $438,000 $400,000 $0
Grand Total $4,282,000 $0 $764,000 $300,000 $100,000 $200,000 $400,000 $1,118,000 $1,400,000 $0

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
03/16/2023 4:56 PM Beth Vollmer Bike path from Hwy 89 to beacon, relocated parking from Jameson Beach road to parking lot (removed parking from native surface soils).
03/09/2023 4:34 PM Judy Weber Project is being removed from the FTIP as that component of the project has been completed. STBG $225,000 & Private Business $29,151 for FY 2020 CON.
01/06/2020 1:33 PM Mike Gabor 2019 - Funds expended to date were for campground and facility type projects.
12/26/2019 2:35 PM Mike Gabor 2019 Projects included Hotel siding, cabin roof replacements, cabin remodeling.