Overview

Basics

Basics
In South Lake Tahoe, from Highway 89 intersection at the "Y" to Trout Creek. Major highway through urban core of South Lake Tahoe with crossings at Truckee River and Trout Creek. Reconstruct highway drainage system and construct stormwater improvements throughout project area. Include right-of-way acquisition for water quality purposes. EA 3C380

Completed
2012
2017
2022
$53,435,000

Joan Davis (D3.FTIP@dot.ca.gov)
12/21/2016
02/03/2023
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes
Postmile: 75.4/77.3

Organizations

EIP Details

EIP Basics

01.01.01.0005 - U.S. Highway 50 Water Quality Improvement Project - "Y" to Trout Creek

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012
City of South Lake Tahoe General Fund (CSLT) $252,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $252,000 $0 $0 $0 $0 $0 $0 $252,000 $0 $0 $0 $0
SHOPP Funds (Caltrans) $53,135,000
Preliminary Engineering $5,041,000 $0 $0 $0 $0 $0 $0 $5,041,000 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $5,650,000 $0 $0 $0 $0 $0 $0 $5,650,000 $0 $0 $0 $0
Construction $42,444,000 $0 $0 $0 $0 $0 $0 $42,444,000 $0 $0 $0 $0
South Tahoe Public Utility District (STPUD) $48,000
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $48,000 $0 $0 $0 $0 $0 $0 $48,000 $0 $0 $0 $0
Grand Total $53,435,000 $0 $0 $0 $0 $0 $0 $53,435,000 $0 $0 $0 $0

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Roads Decommissioned or Retrofitted None 1.9 miles
Miles of Pedestrian and Bicycle Routes Improved or Constructed [Action Performed: Improved], [Path or Route Type: Sidewalk] 3.41 miles

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2017 2018 2019 Total Units
Property Ownership Road Type Treatment Type
California Department of Transportation Paved Retrofitted 2.4 2.4 miles
Total 0 2.4 0 2.4 miles
Miles of Pedestrian and Bicycle Routes Improved or Constructed
2017 2018 2019 Total Units
Action Performed Path or Route Type
Constructed Sidewalk 1.2 1.2 miles
Improved Sidewalk 1.2 1.2 2.4 miles
Total 1.2 1.2 1.2 3.6 miles

No accomplishments to report for:
Year(s) 2020, 2021, 2022
Explanation All construction work was completed on 06/12/2020. No accomplishments to report in 2020, 2021, and 2022

Funding

Expected Funding

Expected Funding
$53,435,000
$53,435,000
$0

Total
City of South Lake Tahoe General Fund (CSLT) $252,000 $252,000 $0
SHOPP Funds (Caltrans) $53,135,000 $53,135,000 $0
South Tahoe Public Utility District (STPUD) $48,000 $48,000 $0
Grand Total $53,435,000 $53,435,000 $0

Reported Expenditures

Reported Expenditures
Total 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012
City of South Lake Tahoe General Fund $252,000 $0 $0 $0 $0 $252,000 $0 $0 $0 $0 $0 $0
SHOPP Funds $53,248,087 $318,998 $4,202,751 $2,896,766 $9,355,283 $8,494,262 $14,763,630 $2,308,227 $3,304,598 $2,111,225 $2,549,352 $2,942,995
South Tahoe Public Utility District $48,000 $0 $0 $0 $0 $48,000 $0 $0 $0 $0 $0 $0
Grand Total $53,548,087 $318,998 $4,202,751 $2,896,766 $9,355,283 $8,794,262 $14,763,630 $2,308,227 $3,304,598 $2,111,225 $2,549,352 $2,942,995

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

01.01.01.0005 - U.S. Highway 50 Water Quality Improvement Project - "Y" to Trout Creek is associated with following groups of projects.

External Links

Notes

Notes
12/13/2019 11:40 AM Joan Davis 19.3 acres treated/pollutant per year for a total of 57.9 acres. The project took 3 years to construct.