Location Information | Location Notes |
---|---|
Postmile: 75.4/77.3
|
California Department of Transportation (Caltrans) | Joan Davis - California Department of Transportation (Caltrans) | |||
City of South Lake Tahoe (CSLT) | Stan Hill - City of South Lake Tahoe (CSLT) | |||
South Tahoe Public Utility District (STPUD) | Donielle Morse - South Tahoe Public Utility District (STPUD) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
Total | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
City of South Lake Tahoe General Fund (CSLT) | $252,000 | ||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $252,000 | $0 | $0 | $0 | $0 | $0 | $0 | $252,000 | $0 | $0 | $0 | $0 | |
SHOPP Funds (Caltrans) | $53,135,000 | ||||||||||||
Preliminary Engineering | $5,041,000 | $0 | $0 | $0 | $0 | $0 | $0 | $5,041,000 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $5,650,000 | $0 | $0 | $0 | $0 | $0 | $0 | $5,650,000 | $0 | $0 | $0 | $0 | |
Construction | $42,444,000 | $0 | $0 | $0 | $0 | $0 | $0 | $42,444,000 | $0 | $0 | $0 | $0 | |
South Tahoe Public Utility District (STPUD) | $48,000 | ||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $48,000 | $0 | $0 | $0 | $0 | $0 | $0 | $48,000 | $0 | $0 | $0 | $0 | |
Grand Total | $53,435,000 | $0 | $0 | $0 | $0 | $0 | $0 | $53,435,000 | $0 | $0 | $0 | $0 |
Miles of Roads Decommissioned or Retrofitted | None | 1.9 | miles |
Miles of Pedestrian and Bicycle Routes Improved or Constructed | [Action Performed: Improved], [Path or Route Type: Sidewalk] | 3.41 | miles |
Miles of Roads Decommissioned or Retrofitted | |||||||
---|---|---|---|---|---|---|---|
|
2017 | 2018 | 2019 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | |||||
California Department of Transportation | Paved | Retrofitted | 2.4 | 2.4 | miles | ||
Total | 0 | 2.4 | 0 | 2.4 | miles |
Miles of Pedestrian and Bicycle Routes Improved or Constructed | ||||||
---|---|---|---|---|---|---|
|
2017 | 2018 | 2019 | Total | Units | |
Action Performed | Path or Route Type | |||||
Constructed | Sidewalk | 1.2 | 1.2 | miles | ||
Improved | Sidewalk | 1.2 | 1.2 | 2.4 | miles | |
Total | 1.2 | 1.2 | 1.2 | 3.6 | miles |
No accomplishments to report for: | |
Year(s) | 2020, 2021, 2022 |
---|---|
Explanation | All construction work was completed on 06/12/2020. No accomplishments to report in 2020, 2021, and 2022 |
Total | |||
---|---|---|---|
City of South Lake Tahoe General Fund (CSLT) | $252,000 | $252,000 | $0 |
SHOPP Funds (Caltrans) | $53,135,000 | $53,135,000 | $0 |
South Tahoe Public Utility District (STPUD) | $48,000 | $48,000 | $0 |
Grand Total | $53,435,000 | $53,435,000 | $0 |
Total | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
City of South Lake Tahoe General Fund | $252,000 | $0 | $0 | $0 | $0 | $252,000 | $0 | $0 | $0 | $0 | $0 | $0 |
SHOPP Funds | $53,248,087 | $318,998 | $4,202,751 | $2,896,766 | $9,355,283 | $8,494,262 | $14,763,630 | $2,308,227 | $3,304,598 | $2,111,225 | $2,549,352 | $2,942,995 |
South Tahoe Public Utility District | $48,000 | $0 | $0 | $0 | $0 | $48,000 | $0 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $53,548,087 | $318,998 | $4,202,751 | $2,896,766 | $9,355,283 | $8,794,262 | $14,763,630 | $2,308,227 | $3,304,598 | $2,111,225 | $2,549,352 | $2,942,995 |
01.01.01.0005 - U.S. Highway 50 Water Quality Improvement Project - "Y" to Trout Creek is associated with following groups of projects.
12/13/2019 11:40 AM | Joan Davis | 19.3 acres treated/pollutant per year for a total of 57.9 acres. The project took 3 years to construct. |