Location Information | Location Notes |
---|---|
|
California Department of Transportation (Caltrans) | Joan Davis - California Department of Transportation (Caltrans) | |||
California Tahoe Conservancy (CTC) | Whitney Brennan - California Tahoe Conservancy (CTC) | |||
North Lake Tahoe Fire Protection District (NLTFPD) | Ryan Dominguez - North Lake Tahoe Fire Protection District (NLTFPD) | |||
North Tahoe Community Alliance (NTCA) | None | |||
Tahoe City Public Utility District (TCPUD) | Kim Boyd - Tahoe City Public Utility District (TCPUD) | |||
Tahoe Fund (Tahoe Fund) | Amy Berry - Tahoe Fund (Tahoe Fund) |
Miles of Trails Developed or Improved | None | miles |
Miles of Pedestrian and Bicycle Routes Improved or Constructed | ||||
---|---|---|---|---|
|
2012 | Total | Units | |
Action Performed | Path or Route Type | |||
Constructed | Class I/Shared Use Path | 1.52 | 1.52 | miles |
Total | 1.52 | 1.52 | miles |
Total | |||
---|---|---|---|
Unknown or Unassigned | $4,316,959 | $4,316,959 | $0 |
Grand Total | $4,316,959 | $4,316,959 | $0 |
Total | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | |
---|---|---|---|---|---|---|---|---|
California Tahoe Conservancy | $2,146,325 | $0 | $712,392 | $1,070,608 | $0 | $255,022 | $0 | $108,303 |
Caltrans Local Assistance (BTA) | $740,370 | $0 | $0 | $740,370 | $0 | $0 | $0 | $0 |
North Lake Tahoe Fire Protection District | $108,699 | $4,888 | $94,980 | $8,831 | $0 | $0 | $0 | $0 |
North Tahoe Community Alliance | $810,825 | $8,169 | $511,526 | $291,130 | $0 | $0 | $0 | $0 |
Tahoe City Public Utility District | $490,740 | $0 | $0 | $0 | $490,740 | $0 | $0 | $0 |
Tahoe Fund | $20,000 | $0 | $20,000 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $4,316,959 | $13,057 | $1,338,898 | $2,110,939 | $490,740 | $255,022 | $0 | $108,303 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
10/16/2015 12:02 PM | Jeanne McNamara | Phase IIB completed 0.06 miles of trail; Phase IV completed 0.12 miles; and Phases V,VI, VII completed 0.8 miles |