Location Information | Location Notes |
---|---|
|
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Brent Moore - Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | |||
Washoe County, NV (WACO) | Dave Solaro - Washoe County, NV (WACO) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
Miles of Roads Decommissioned or Retrofitted | None | miles |
Miles of Roads Decommissioned or Retrofitted | |||||
---|---|---|---|---|---|
|
2017 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | |||
Washoe County | Paved | Retrofitted | 2.4 | 2.4 | miles |
Total | 2.4 | 2.4 | miles |
No accomplishments to report for: | |
Year(s) | 2018 |
---|---|
Explanation | Construction/implementation was completed in 2017. Project was closed out during 2018, with no additional performance measures to report. |
Total | |||
---|---|---|---|
Southern Nevada Public Land Management Act (USFS - LTBMU) | $1,927,500 | $1,927,500 | $0 |
Tahoe Bonds Act (NDSL) | $1,899,000 | $1,899,000 | $0 |
Washoe County General Fund (WACO) | $202,579 | $202,579 | $0 |
Grand Total | $4,029,079 | $4,029,079 | $0 |
Total | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | |
---|---|---|---|---|---|---|---|---|
Southern Nevada Public Land Management Act | $1,927,500 | $989,162 | $701,151 | $146,685 | $90,502 | $0 | $0 | $0 |
Tahoe Bonds Act | $1,899,000 | $913,744 | $736,209 | $154,020 | $95,027 | $0 | $0 | $0 |
Washoe County General Fund | $202,579 | $202,579 | $0 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $4,029,079 | $2,105,485 | $1,437,360 | $300,705 | $185,529 | $0 | $0 | $0 |
No Related Projects set for this project.
No external links entered.
12/20/2018 3:45 PM | Ben Jesch | Construction/implementation was completed in 2017. Project was closed out during 2018. | ||
12/30/2016 9:08 AM | Kris Klein | The project is at 75% design as of October 1, 2016. | ||
12/30/2016 9:05 AM | Kris Klein | Annual expenditures include all reimbursement requests and payments from funders through September 30, 2016 (end of the water year). | ||
12/28/2016 3:59 PM | Ben Jesch | 2016 Expenditures are from 1/1/16 through 9/30/16. | ||
01/09/2015 2:53 PM | Kimble Corbridge | Secured funding includes $1.5M from USFS and $1.5M from NDSL | ||
01/09/2015 2:52 PM | Kimble Corbridge | NDSL funding and expenditure amounts include 5% admin. costs based on the amount of NDSL funding. | ||
01/09/2015 2:50 PM | Kimble Corbridge | Annual expenditures include all reimbursement requests for time periods that end in the year indicated. |