Location Information | Location Notes |
---|---|
|
California Department of Water Resources (California DWR) | None | |||
El Dorado County, CA (ELDO) | Donaldo Palaroan - El Dorado County, CA (ELDO) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
No expected performance measures set for this project.
Miles of Roads Decommissioned or Retrofitted | ||||||||
---|---|---|---|---|---|---|---|---|
|
2013 | 2014 | 2015 | 2016 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | ||||||
El Dorado County | Paved | Retrofitted | 1.5 | 0.5 | 0.5 | 0.5 | 3 | miles |
Total | 1.5 | 0.5 | 0.5 | 0.5 | 3 | miles |
No accomplishments to report for: | |
Year(s) | 2017, 2018 |
---|---|
Explanation | Construction was completed prior to 2017/2018. |
Total | |||
---|---|---|---|
Integrated Regional Water Management Plan Funds (IWRMP) (California DWR) | $232,283 | $232,283 | $0 |
Southern Nevada Public Land Management Act (USFS - LTBMU) | $705,975 | $705,975 | $0 |
WQ Mitigation Funds (TRPA) | $28,828 | $28,828 | $0 |
Grand Total | $967,086 | $967,086 | $0 |
Total | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Integrated Regional Water Management Plan Funds (I... | $204,996 | $0 | $0 | $41,858 | $11,822 | $18,738 | $81,743 | $50,835 | $0 | $0 | $0 | $0 |
Southern Nevada Public Land Management Act | $690,040 | $0 | $379 | $0 | $13,493 | $25,000 | $370,765 | $159,631 | $75,182 | $25,875 | $19,715 | $0 |
WQ Mitigation Funds | $32,830 | $0 | $0 | $0 | $0 | $4,000 | $0 | $3,031 | $8,134 | $0 | $1,763 | $15,902 |
Grand Total | $927,866 | $0 | $379 | $41,858 | $25,315 | $47,738 | $452,508 | $213,497 | $83,316 | $25,875 | $21,478 | $15,902 |