Location Information | Location Notes |
---|---|
|
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Brent Moore - Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | |||
Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | Kevin Fromherz - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
U.S. Army Corps of Engineers (USACOE) | None |
Linear Feet of Stream Channel Restored or Enhanced | None | linear feet | |
Acres of SEZ Restored or Enhanced | None | acres |
Miles of Roads Decommissioned or Retrofitted | |||||
---|---|---|---|---|---|
|
2015 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | |||
Nevada Division of State Lands | Unpaved | Retrofitted | 5 | 5 | miles |
Total | 5 | 5 | miles |
Linear Feet of Stream Channel Restored or Enhanced | ||||
---|---|---|---|---|
|
2015 | Total | Units | |
Action Performed | Watershed | |||
Restored | Slaughter House | 67 | 67 | linear feet |
Total | 67 | 67 | linear feet |
Acres of SEZ Restored or Enhanced | |||
---|---|---|---|
|
2015 | Total | Units |
Action Performed | |||
Restored | 0.57 | 0.57 | acres |
Total | 0.57 | 0.57 | acres |
Miles of Trails Developed or Improved | |||
---|---|---|---|
|
2015 | Total | Units |
Action Performed | |||
Improved | 1.75 | 1.75 | miles |
Total | 1.75 | 1.75 | miles |
No accomplishments to report for: | |
Year(s) | 2013, 2014 |
---|---|
Explanation | Due to some permitting issues, the project has not been completed. The project is planned to go to construction in 2015. |
Total | |||
---|---|---|---|
Unknown or Unassigned | $941,640 | $941,640 | $0 |
Grand Total | $941,640 | $941,640 | $0 |
Total | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | |
---|---|---|---|---|---|---|---|---|
Lake Tahoe License Plate Program | $60,000 | $0 | $60,000 | $0 | $0 | $0 | $0 | $0 |
Question 1 (NV State Parks) | $37,707 | $0 | $37,707 | $0 | $0 | $0 | $0 | $0 |
Tahoe Bonds Act | $434,579 | $250,576 | $25,388 | $14,755 | $46,641 | $97,219 | $0 | $0 |
U.S. Army Corps of Engineers | $409,354 | $0 | $30,562 | $41,076 | $139,922 | $50,481 | $0 | $147,313 |
Grand Total | $941,640 | $250,576 | $153,657 | $55,831 | $186,563 | $147,700 | $0 | $147,313 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
No notes entered.