Location Information | Location Notes |
---|---|
|
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
No expected performance measures set for this project.
Miles of Pedestrian and Bicycle Routes Improved or Constructed | |||||
---|---|---|---|---|---|
|
2009 | 2010 | Total | Units | |
Action Performed | Path or Route Type | ||||
Constructed | Class I/Shared Use Path | 3 | 3 | miles | |
Total | 0 | 3 | 3 | miles |
Miles of Trails Developed or Improved | ||||
---|---|---|---|---|
|
2009 | 2010 | Total | Units |
Action Performed | ||||
Improved | 22.5 | 4.2 | 26.7 | miles |
Total | 22.5 | 4.2 | 26.7 | miles |
No accomplishments to report for: | |
Year(s) | 2011, 2012, 2013, 2014, 2015 |
---|---|
Explanation | Ongoing need. Will proceed as funding becomes available. |
Total | |||
---|---|---|---|
Unknown or Unassigned | $1,653,000 | $1,653,000 | $0 |
Grand Total | $1,653,000 | $1,653,000 | $0 |
Total | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Southern Nevada Public Land Management Act | $1,653,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $553,000 | $1,100,000 | $0 | $0 |
Grand Total | $1,653,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $553,000 | $1,100,000 | $0 | $0 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
05/21/2014 6:04 PM | System | Round 10 BLM SNPLMA Project #F147 is Phase III which follows Round 9 Phase II. In addition to the reported performance achievements for 2010, 9.5 miles of system and non-system trails are planned to be obliterated and construction of 2 trail crossing upgrades (multi-use bridge & one stream ford). Proposed action for this project may change as a result of the ongoing NEPA process for the Angora Fire Restoration Project. | ||
05/21/2014 6:03 PM | System | Round 9 BLM SNPLMA Project #F128. This Phase II project follows Round 8 SNPLMA Project - Basinwide Trail ATM Phase I. In addition to the reported performance achievements for 2009, 4 miles of trails are planned to be obliterated, 1 stream crossing is planned for restoration and 3 stream crossings are planned to be upgraded. | ||
05/21/2014 6:02 PM | System | Phase III - Project funds the final stages of design & construction of the Angora Fire Trail Project to provide water quality retrofit of the non-motorized recreation trails in & near the Angora Fire area. BMPs will be installed at public trail system access point near the intersection of Sawmill Rd and Lake Tahoe Blvd. | ||
05/21/2014 6:01 PM | System | Round 9 BLM SNPLMA Project #F128. This Phase II project follows Round 8 SNPLMA Project - Basinwide Trail ATM Phase I. |