Location Information | Location Notes |
---|---|
|
Tahoe Fund (Tahoe Fund) | Amy Berry - Tahoe Fund (Tahoe Fund) | |||
U.S. Federal Highway Administration (FHWA) | Matt Ambroziak - U.S. Department of Transportation (US DOT) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
This project is on the EIP 5-year list.
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
Total | 2027 | 2026 | 2025 | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Surface Transportation Block Grant (STBG) - California (FHWA) | $308,000 | ||||||||||||||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $308,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $308,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Grand Total | $308,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $308,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
No expected performance measures set for this project.
Facilities Improved or Created | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | Total | Units | ||
Action Performed | Primary Facility Type | Primary Purpose of Facility | ||||||||||||
Improved | Buildings & Grounds | Recreation | 3 | 0 | 2 | 1 | 1 | 1 | 0 | 0 | 2 | 10 | number | |
Improved | Miscellaneous Structures | Recreation | 1 | 1 | number | |||||||||
Total | 3 | 0 | 2 | 1 | 1 | 1 | 1 | 0 | 0 | 2 | 11 | number |
Total | |||
---|---|---|---|
Southern Nevada Public Land Management Act (USFS - LTBMU) | $4,451,628 | $4,451,628 | $0 |
Surface Transportation Block Grant (STBG) - California (FHWA) | $308,000 | $308,000 | $0 |
Tahoe Fund (Tahoe Fund) | $83,000 | $82,000 | $1,000 |
U.S. Forest Service (USFS - LTBMU) | $1,163,000 | $963,000 | $200,000 |
Grand Total | $6,005,628 | $5,804,628 | $201,000 |
Total | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Southern Nevada Public Land Management Act | $4,451,628 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $2,204,500 | $500,000 | $985,000 | $243,328 | $0 | $18,800 | $500,000 | $0 | $0 |
Surface Transportation Block Grant (STBG) - Califo... | $308,000 | $0 | $308,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Tahoe Fund | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
U.S. Forest Service | $963,000 | $0 | $0 | $0 | $0 | $41,000 | $43,000 | $25,000 | $80,000 | $0 | $0 | $347,200 | $365,800 | $61,000 | $0 | $0 | $0 | $0 |
Grand Total | $5,722,628 | $0 | $308,000 | $0 | $0 | $41,000 | $43,000 | $25,000 | $80,000 | $2,204,500 | $500,000 | $1,332,200 | $609,128 | $61,000 | $18,800 | $500,000 | $0 | $0 |
No Related Projects set for this project.
No external links entered.
03/16/2023 4:26 PM | Judy Weber | Project is removed from FTIP list. Project components have been completed. STBG $308,000 & Tahoe Fund $82,000 | ||
02/09/2023 1:06 PM | Beth Vollmer | Tahoe fund money is outside of the FTIP. Funding was for signage improvements at Taylor Creek | ||
02/03/2023 9:43 AM | Beth Vollmer | Parking improvements at Kiva point and Valhalla. | ||
02/08/2021 11:18 AM | Beth Vollmer | No work done in 2020 | ||
12/26/2019 1:29 PM | Mike Gabor | 2019 projects included Twin Cabin siding replacement | ||
12/26/2019 1:28 PM | Mike Gabor | 2018 projects included electrical upgrades, irrigation system efficiency upgrades and building siding replacement. | ||
12/26/2017 1:54 PM | Mike Gabor | Work in 2017 included the rehabilitation of the Valhalla Boathouse theatre water system including the installation of a back flow prevention device. | ||
01/08/2016 3:28 PM | Genevieve Villemaire | The project has been funded by four SNPLMA grants thusfar. The first two grants laid the planning groundwork for the BMPs designed under the third grant, including NEPA analysis, survey work and permitting. Implementation of the designed BMP retrofit is funded under a fourth and final SNPLMA grant and implementation began on the North side of Hwy 89 in 2015. South side improvement implementation will start during 2016. | ||
05/21/2014 6:01 PM | System | Round 9 BLM SNPLMA Project # F131. Project follows Round 5 SNPLMA Project - Camp Rich Vision Plan and Campgrounds BMP Retrofit. This project is first of three phases needed to complete the final planning and design for rehabilitation of the three campgrounds to current environmental protection standards. |