Overview

Basics

Basics
Sierra Tract ECP Phase 3/4: Erosion source controls and stormwater treatment facilities associated with grantees roadways. Improvements will include re-vegetation. of disturbed soils (e.g. paved gutters, rock lined channels), infiltration and sedimentation facilities. Phase 3 and Phase 4 were combined to Phase 3/4. Combined Phase 3/4 includes high priority areas that were identified with the PLRM process.

Completed
2006
2015
2016
$4,903,428

Stan Hill (shill@cityofslt.us)
11/18/2016
11/18/2016
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

01.01.01.0056 - Sierra Tract Erosion Control Project Phase 4
693.4

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Roads Decommissioned or Retrofitted None 0.6 miles
Miles of Street Sweeping None 0.6 miles

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2015 2016 Total Units
Property Ownership Road Type Treatment Type
City of South Lake Tahoe Paved Retrofitted 1 2.2 3.2 miles
Total 1 2.2 3.2 miles
Miles of Street Sweeping
2015 2016 Total Units
Equipment Type Property Ownership
High-Efficiency Vacuum-Assisted Dry Sweeper City of South Lake Tahoe 3.5 3.5 7 miles
Total 3.5 3.5 7 miles
Acres of SEZ Restored or Enhanced
2015 2016 Total Units
Action Performed
Enhanced 0.25 2 2.25 acres
Total 0.25 2 2.25 acres

No accomplishments to report for:
Year(s) 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2013, 2014
Explanation Project under construction.

Funding

Expected Funding

Expected Funding
$4,903,428
$4,903,428
$0

Total
Unknown or Unassigned $4,903,428 $4,903,428 $0
Grand Total $4,903,428 $4,903,428 $0

Reported Expenditures

Reported Expenditures
Total 2016 2015 2014 2013 2012 2011 2010 2009 2008 2007
California Tahoe Conservancy $802,028 $13,800 $197,813 $95,370 $367,097 $17,864 $0 $0 $57,939 $50,359 $1,786
Proposition 84 (Lahontan) $2,811,164 $1,791,937 $1,019,227 $0 $0 $0 $0 $0 $0 $0 $0
South Tahoe Public Utility District $89,115 $58,731 $30,384 $0 $0 $0 $0 $0 $0 $0 $0
Southern Nevada Public Land Management Act $1,201,121 $959,974 $166,042 $12,324 $2,504 $773 $6,701 $4,188 $4,793 $43,822 $0
Grand Total $4,903,428 $2,824,442 $1,413,466 $107,694 $369,601 $18,637 $6,701 $4,188 $62,732 $94,181 $1,786

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
05/21/2014 6:01 PM System 2012 funding: Sierra TractPhases 3 & 4 reported together