Overview

Basics

Basics
This project included many small specific areas that were identified for source control and conveyance as part of the Washoe County EIP Project Assessment completed in February of 2006. The project areas for this project are within project boundaries of several completed EIP projects however the improvements constructed with this project were not included as part of the older projects. Treatment areas within the project area were prioritized based on fine sediment particle (FSP) loading identified in the "Nevada Tahoe TMDL Implementing Agencies Stormwater Load Reduction Plans Baseline and Existing Conditions Final Technical Documents" dated December 31, 2013.

Completed
2010
2014
2015
$1,908,350

Dave Solaro (dsolaro@washoecounty.gov)
06/01/2014
01/22/2016
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

01.01.01.0058 - Central Incline Village Water Quality Improvement Project - Phase I

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2014 Total Units
Property Ownership Road Type Treatment Type
Washoe County Paved Retrofitted 4.19 4.19 miles
Total 4.19 4.19 miles

No accomplishments to report for:
Year(s) 2011, 2012, 2013, 2015
Explanation Improvements were implemented during the 2014 construction season.

Funding

Expected Funding

Expected Funding
$1,908,350
$1,908,350
$0

Total
Unknown or Unassigned $1,908,350 $1,908,350 $0
Grand Total $1,908,350 $1,908,350 $0

Reported Expenditures

Reported Expenditures
Total 2015 2014 2013 2012 2011 2010
Southern Nevada Public Land Management Act $926,383 $69,829 $706,615 $89,035 $47,380 $13,524 $0
Tahoe Bonds Act $981,967 $74,019 $749,012 $94,377 $50,623 $13,936 $0
Grand Total $1,908,350 $143,848 $1,455,627 $183,412 $98,003 $27,460 $0

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
12/11/2015 2:46 PM Joaquin Tabbada Total Miles Treated (retrofitted) includes all County roads draining to BMP's installed with project.
07/22/2015 9:19 AM Jeanne McNamara The old EIP projects are EIP numbers 2312A - Fairway Phase IIIa, 231C - Village Boulevard, 669B - Incline Village Commercial and Lower Wood Creek Ph II and 669C - Incline Village Commercial and Lower Wood Creek Ph III.
12/31/2014 3:46 PM Kris Klein Annual expenditures include all reimbursement requests for time periods that end in the year indicated.
12/31/2014 3:41 PM Kris Klein NDSL funding and expenditure amounts include 3% administrative costs based on the total project cost.
12/31/2014 3:40 PM Kris Klein Secured Funding includes $1,325,000 from NDSL and $1,250,000 from USFS