Location Information | Location Notes |
---|---|
|
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Brent Moore - Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | |||
Washoe County, NV (WACO) | Dave Solaro - Washoe County, NV (WACO) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
No expected performance measures set for this project.
Miles of Roads Decommissioned or Retrofitted | |||||
---|---|---|---|---|---|
|
2014 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | |||
Washoe County | Paved | Retrofitted | 4.19 | 4.19 | miles |
Total | 4.19 | 4.19 | miles |
No accomplishments to report for: | |
Year(s) | 2011, 2012, 2013, 2015 |
---|---|
Explanation | Improvements were implemented during the 2014 construction season. |
Total | |||
---|---|---|---|
Unknown or Unassigned | $1,908,350 | $1,908,350 | $0 |
Grand Total | $1,908,350 | $1,908,350 | $0 |
Total | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | |
---|---|---|---|---|---|---|---|
Southern Nevada Public Land Management Act | $926,383 | $69,829 | $706,615 | $89,035 | $47,380 | $13,524 | $0 |
Tahoe Bonds Act | $981,967 | $74,019 | $749,012 | $94,377 | $50,623 | $13,936 | $0 |
Grand Total | $1,908,350 | $143,848 | $1,455,627 | $183,412 | $98,003 | $27,460 | $0 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
12/11/2015 2:46 PM | Joaquin Tabbada | Total Miles Treated (retrofitted) includes all County roads draining to BMP's installed with project. | ||
07/22/2015 9:19 AM | Jeanne McNamara | The old EIP projects are EIP numbers 2312A - Fairway Phase IIIa, 231C - Village Boulevard, 669B - Incline Village Commercial and Lower Wood Creek Ph II and 669C - Incline Village Commercial and Lower Wood Creek Ph III. | ||
12/31/2014 3:46 PM | Kris Klein | Annual expenditures include all reimbursement requests for time periods that end in the year indicated. | ||
12/31/2014 3:41 PM | Kris Klein | NDSL funding and expenditure amounts include 3% administrative costs based on the total project cost. | ||
12/31/2014 3:40 PM | Kris Klein | Secured Funding includes $1,325,000 from NDSL and $1,250,000 from USFS |