Location Information | Location Notes |
---|---|
|
California Tahoe Conservancy (CTC) | Whitney Brennan - California Tahoe Conservancy (CTC) | |||
El Dorado County, CA (ELDO) | Donaldo Palaroan - El Dorado County, CA (ELDO) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
Miles of Roads Decommissioned or Retrofitted | None | miles |
Miles of Roads Decommissioned or Retrofitted | ||||||
---|---|---|---|---|---|---|
|
2015 | 2016 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | ||||
El Dorado County | Paved | Retrofitted | 0.6 | 0.6 | 1.2 | miles |
Total | 0.6 | 0.6 | 1.2 | miles |
No accomplishments to report for: | |
Year(s) | 2014, 2017, 2018 |
---|---|
Explanation | 2014 - Project was not complete. 2017/2018 is for Post Construction Monitoring |
Total | |||
---|---|---|---|
California Tahoe Conservancy (CTC) | $189,941 | $189,941 | $0 |
Southern Nevada Public Land Management Act (USFS - LTBMU) | $97,312 | $97,312 | $0 |
WQ Mitigation Funds (TRPA) | $50,429 | $50,429 | $0 |
Grand Total | $337,682 | $337,682 | $0 |
Total | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
California Tahoe Conservancy | $227,001 | $0 | $0 | $0 | $0 | $223,710 | $3,291 | $0 | $0 | $0 | $0 | $0 | $0 |
Southern Nevada Public Land Management Act | $89,929 | $0 | $0 | $0 | $0 | $2,000 | $37,867 | $38,255 | $11,807 | $0 | $0 | $0 | $0 |
WQ Mitigation Funds | $12,368 | $0 | $0 | $1,284 | $2,323 | $6,099 | $118 | $0 | $274 | $2,270 | $0 | $0 | $0 |
Grand Total | $329,298 | $0 | $0 | $1,284 | $2,323 | $231,809 | $41,276 | $38,255 | $12,081 | $2,270 | $0 | $0 | $0 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
No notes entered.