| Location Information | Location Notes |
|---|---|
|
|
|
| U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
Not provided
| Linear Feet of Stream Channel Restored or Enhanced | None | linear feet | |
| Acres of SEZ Restored or Enhanced | None | acres |
| Linear Feet of Stream Channel Restored or Enhanced | |||||||
|---|---|---|---|---|---|---|---|
|
|
2013 | 2014 | 2016 | 2017 | Total | Units | |
| Action Performed | Watershed | ||||||
| Restored | Upper Truckee River | 3,000 | 4,000 | 7,340 | 14,340 | linear feet | |
| Total | 3,000 | 4,000 | 7,340 | 0 | 14,340 | linear feet | |
| Acres of SEZ Restored or Enhanced | ||||||
|---|---|---|---|---|---|---|
|
|
2013 | 2014 | 2016 | 2017 | Total | Units |
| Action Performed | ||||||
| Enhanced | 3 | 3 | acres | |||
| Restored | 120 | 120 | acres | |||
| Total | 0 | 0 | 120 | 3 | 123 | acres |
| No accomplishments to report for: | |
| Year(s) | 2015 |
|---|---|
| Explanation | Conducted irrigation and maintained BMPs. |
| Total | |||
|---|---|---|---|
| Unknown or Unassigned | $9,202,000 | $9,202,000 | $0 |
| Grand Total | $9,202,000 | $9,202,000 | $0 |
| Total | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | |
|---|---|---|---|---|---|---|---|---|---|---|
| Southern Nevada Public Land Management Act | $9,202,000 | $500,000 | $2,600,000 | $1,040,000 | $1,700,000 | $1,710,000 | $352,000 | $250,000 | $550,000 | $500,000 |
| Grand Total | $9,202,000 | $500,000 | $2,600,000 | $1,040,000 | $1,700,000 | $1,710,000 | $352,000 | $250,000 | $550,000 | $500,000 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
| 12/09/2015 4:54 PM | Sue Norman | 2015 Seasoning year to let vegetation on newly constructed channels establish. Conducted irrigation and maintained BMPs. | ||
| 12/09/2015 4:52 PM | Sue Norman | Four thousand feet of new stream channel constructed in 2014. | ||
| 07/23/2014 2:19 PM | Jeanne McNamara | Three thousand feet of new stream channel constructed in 2013. Project implementation to continue through 2016. |