Location Information | Location Notes |
---|---|
|
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
No expected performance measures set for this project.
Miles of Roads Decommissioned or Retrofitted | ||||||||
---|---|---|---|---|---|---|---|---|
|
2012 | 2013 | 2014 | 2015 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | ||||||
U.S. Forest Service | Unpaved | Retrofitted | 1 | 1 | miles | |||
Total | 1 | 0 | 0 | 0 | 1 | miles |
Acres of Invasive Species Inventoried | ||||||
---|---|---|---|---|---|---|
|
2012 | 2013 | 2014 | 2015 | Total | Units |
Invasive Species Type | ||||||
Terrestrial | 75 | 0 | 0 | 75 | acres | |
Total | 0 | 75 | 0 | 0 | 75 | acres |
Miles of Trails Developed or Improved | ||||||
---|---|---|---|---|---|---|
|
2012 | 2013 | 2014 | 2015 | Total | Units |
Action Performed | ||||||
Improved | 1 | 1 | miles | |||
Total | 1 | 0 | 0 | 0 | 1 | miles |
Facilities Improved or Created | ||||||||
---|---|---|---|---|---|---|---|---|
|
2012 | 2013 | 2014 | 2015 | Total | Units | ||
Action Performed | Primary Facility Type | Primary Purpose of Facility | ||||||
Improved | Buildings & Grounds | Recreation | 3 | 3 | 2 | 0 | 8 | number |
Total | 3 | 3 | 2 | 0 | 8 | number |
No accomplishments to report for: | |
Year(s) | 2011 |
---|---|
Explanation | Project planning and design during this year. |
Total | |||
---|---|---|---|
Unknown or Unassigned | $2,425,116 | $2,425,116 | $0 |
Grand Total | $2,425,116 | $2,425,116 | $0 |
Total | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | |
---|---|---|---|---|---|---|---|---|---|
Southern Nevada Public Land Management Act | $1,751,116 | $527,066 | $313,000 | $911,050 | $0 | $0 | $0 | $0 | $0 |
U.S. Forest Service | $674,000 | $0 | $0 | $0 | $674,000 | $0 | $0 | $0 | $0 |
Grand Total | $2,425,116 | $527,066 | $313,000 | $911,050 | $674,000 | $0 | $0 | $0 | $0 |
No watersheds set for this project.
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
01/15/2016 4:17 PM | Genevieve Villemaire | NEPA analysis was performed for Forest Service historic facilities: Old Mill, Meiss Cabin, the Tallac Historic Site, and Newhall House. The analysis, performed by forest service specialists, determined only the Newhall House facility required improvements resulting in the implementation of facility, road and trail BMPs . Additionally, planning, NEPA analysis, design, implementation, and monitoring of water quality protection Best Management Practices (BMPs) took place at Forest Service administrative sites: Meyers Work Center, Fallen Leaf Campground, and Logan Shoals Overlook facilities. Planning, NEPA, and design was performed for William Kent Campground facility. Each of these facilities required retrofit activities to address deficiencies in water quality protection standards. |