To zoom, hold down the Shift key and drag a rectangle.
|
|
Location Information | Location Notes |
---|---|
|
Tahoe Fund (Tahoe Fund) | Amy Berry - Tahoe Fund (Tahoe Fund) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Army Corps of Engineers (USACOE) | None | |||
U.S. Bureau of Land Management (BLM) | None | |||
U.S. Fish and Wildlife Service (USFWS) | Roy Ulibarri - U.S. Fish and Wildlife Service (USFWS) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
This project is on the EIP 5-year list.
Linear Feet of Stream Channel Restored or Enhanced | None | linear feet | |
Acres of Habitat Restored or Enhanced | None | acres | |
Acres Treated for Invasive Species | None | acres |
Acres Treated for Invasive Species | |||||||||
---|---|---|---|---|---|---|---|---|---|
|
2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | Total | Units |
Invasive Species Type | |||||||||
Aquatic | 6 | 16 | 18 | 55.24 | 95.24 | acres | |||
Total | 0 | 0 | 0 | 6 | 16 | 18 | 55.24 | 95.24 | acres |
Acres of Invasive Species Inventoried | |||||||||
---|---|---|---|---|---|---|---|---|---|
|
2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | Total | Units |
Invasive Species Type | |||||||||
Aquatic | 10 | 25 | 25 | 25 | 18 | 18 | 259.54 | 380.54 | acres |
Total | 10 | 25 | 25 | 25 | 18 | 18 | 259.54 | 380.54 | acres |
Total | |||
---|---|---|---|
Lake Tahoe Restoration Act (TRPA) | $2,135,724 | $2,135,724 | $0 |
Lake Tahoe Restoration Act (USFS - LTBMU) | $2,336,844 | $1,836,844 | $500,000 |
Shoreline Fee (TRPA) | $49,645 | $49,645 | $0 |
Southern Nevada Public Land Management Act (BLM) | $450,000 | $450,000 | $0 |
Southern Nevada Public Land Management Act (USFS - LTBMU) | $437,426 | $437,426 | $0 |
Tahoe Fund (Tahoe Fund) | $100,000 | $100,000 | $0 |
U.S. Army Corps of Engineers (USACOE) | $312,032 | $312,032 | $0 |
Grand Total | $5,821,671 | $5,321,671 | $500,000 |
Total | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Bipartisan Infrastructure Law | $1,370,174 | $278,677 | $854,427 | $237,070 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Lake Tahoe Restoration Act | $768,668 | $0 | $0 | $405,815 | $362,853 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Lake Tahoe Restoration Act | $3,147,386 | $1,394,076 | $183,295 | $600,000 | $970,015 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Southern Nevada Public Land Management Act | $870,505 | $73,869 | $279,791 | $66,845 | $0 | $0 | $0 | $0 | $0 | $30,000 | $140,000 | $140,000 | $110,000 | $30,000 |
Tahoe Fund | $100,500 | $500 | $0 | $100,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
U.S. Army Corps of Engineers | $211,836 | $0 | $0 | $11,685 | $200,151 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $6,469,069 | $1,747,122 | $1,317,513 | $1,421,415 | $1,533,019 | $0 | $0 | $0 | $0 | $30,000 | $140,000 | $140,000 | $110,000 | $30,000 |
No watersheds set for this project.
01.02.01.0034 - Taylor and Tallac Ecosystem Restoration is associated with following groups of projects.
01/31/2025 12:09 PM | Emily Justice | In the first half of 2024, continued sediment buildup and barrier integrity monitoring work occurred and planning began for full removal of barriers in the fall. Prior to full removal, the contractors conducted a survey upstream of the barriers to ensure no new upstream infestations would re-infest the barrier site. Additionally, below-barrier root checks were done in a dozen sites across Taylor and Tallac Creeks which confirmed no viable roots remained. Finally, efforts to complete control offshore of Taylor Creek mouth was prioritized to reduce nearby fragments that could float into and re-infest the barrier sites. In August, monitoring showed elevated levels of sediment buildup on barriers near Taylor Creek mouth and approximately 40 barriers were removed early before the sediment levels made removal too difficult and costly. In October, crews began full removal of the remaining barriers in Taylor and Tallac Creeks and have been able to continue work through December thanks to continued dry weather. At the end of December 2024, all barriers and materials had been removed from Tallac Creek and approximately 25% of barriers remained in Taylor Creek. We anticipate to continue work through spring, as weather allows. Acres inventoried and treated in 2024 saw a significant increase due to additional hand pulling and offshore work throughout 2024 as the project wraps up. Hand pulling acreage is tallied for each visit to represent effort expended to complete the work. Next steps for 2025 will be: release an RFP and award a contract for a long-term monitoring effort. |
||
01/11/2024 4:00 PM | Sarah Muskopf | TRPA will add financials after USFS submittal. I had to add $0 to all in order to submit | ||
01/07/2024 1:42 PM | Sarah Muskopf | Updated for USFS. TRPA needs to add expenditures for 2023. | ||
01/06/2021 4:59 PM | Sarah Muskopf | Beth and Kim - I was hoping to take "Phase 1" out of the title and just call Taylor and Tallac Restoration. I updated the project cost to make the project whole. Sounds like Kim was thinking of splitting the project? Should we discuss? | ||
01/06/2021 4:58 PM | Sarah Muskopf | Funding in 2020 was used to award contract and prep for implementation Spring 2021. Contract was awarded to Marine Taxonomic Services. This infestation continues to grow and expanded by four acres between 2019 and 2020. | ||
08/21/2020 12:14 PM | Kimberly Chevallier | Kim Updated this project to reflect the AIS project. Need to input a new project that just captures the historical NEPA planning and move those expenditures there. | ||
12/18/2019 1:45 PM | Sarah Muskopf | 12/18/2019: Sarah Muskopf update expected project costs based on recent aquatic invasive weed surveys. Added maps from these survey efforts. | ||
11/26/2018 12:54 PM | Sarah Muskopf | Updated AIS funding based on 2018 inventories (10 acres monitored/ 6 acres infested). Updated accomplishments. |