Overview

Basics

Basics
This project reports TMDL implementation accomplishments performed by Non-Urban TMDL Implementation Partners. In order to avoid duplication of results, accomplishments should only be entered for TMDL PMs that are not reported under individual EIP projects. Data should be entered for actions that are completed. Expenditure data is not required to be reported here, but is entered on a project-level basis. For more information on the implementation of the Lake Tahoe TMDL, go to: https://clarity.laketahoeinfo.org/

Implementation
2018
2018
2035
$800,000

Sarah Rasmussen (srasmussen@skihomewood.com)
06/01/2014
02/05/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

Organizations
Homewood Ski Resort (Homewood) Sarah Rasmussen - Homewood Ski Resort (Homewood)
Private (Private) Kat McIntyre - Tahoe Regional Planning Agency (TRPA)

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Performance Measures

Expected Performance Measures

Reported Performance Measures

Reported Performance Measures
Linear Feet of Stream Channel Restored or Enhanced
2018 2019 2020 2021 2022 2023 Total Units
Action Performed Watershed
Enhanced Homewood Creek 10 0 0 10 linear feet
Total 0 0 0 10 0 0 10 linear feet
Forest Roads Inspected and Maintained
2018 2019 2020 2021 2022 2023 Total Units
Ownership Road Operation Type Road Type
Homewood Maintained Unpaved 3 5 10 5 5 5 33 miles
Total 3 5 10 5 5 5 33 miles
Forest Roads Created
2018 2019 2020 2021 2022 2023 Total Units
Ownership Road Type
Homewood Unpaved 0.25 0.25 0 0 0.5 miles
Total 0 0 0.25 0.25 0 0 0.5 miles
Disturbed Areas Restored, Enhanced, or Created
2018 2019 2020 2021 2022 2023 Total Units
Disturbed Area Treatment Type Ownership
Restored Homewood 5 40 20 2 2 0 69 acres
Total 5 40 20 2 2 0 69 acres
Forest Upland Facilities Retrofitted for Stormwater
2018 2019 2020 2021 2022 2023 Total Units
Ownership Type of Retrofit Action
Homewood Maintained 32 11 20 2 5 0 70 number
Total 32 11 20 2 5 0 70 number

Funding

Expected Funding

Expected Funding
$800,000
$0
$800,000

No funding sources identified for this project.

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018
Private (Business) $255,000 $5,000 $50,000 $50,000 $50,000 $50,000 $50,000
Grand Total $255,000 $5,000 $50,000 $50,000 $50,000 $50,000 $50,000

Photos

Photos

No photos available.

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

No Threshold Categories set for this project.

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
06/10/2022 3:13 PM Sarah Rasmussen Current forest roads maintained.