Overview

Basics

Basics
This initial capital project includes development of a strategic build-out of a regional ferry system, including evaluation of fuel type, coordination with emergency managers for evacuation, and private water taxis operations. Preliminary engineering, environmental, final design and construction of the primary north and south shore ferry terminals,maintenance facilities, and purchasing the high-speed ferry boats necessary for the service are included. Once service is established, this project will become part of TTD's transit operations and coordinate with water taxi services provided by private operators to meet peak demand.

Planning/Design
2009
2029
2031
$186,500,000

01/06/2017
02/07/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

Organizations

EIP Details

EIP Basics

03.02.01.0011 - Lake Tahoe Waterborne Ferry Project

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2031 2030 2029 2028 2027 2026 2025 2024 2023 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012 2011 2010 2009
Federal Lands Highway Funding (FHWA) $847,520
Preliminary Engineering $847,520 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $847,520
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grand Total $847,520 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $847,520

Performance Measures

Expected Performance Measures

Expected Performance Measures
Pounds of Air Pollutants Removed or Avoided by Project None pounds

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$186,500,000
$847,520
$185,652,480
($5,000,000 identified as )

Total
Federal Lands Highway Funding (FHWA) $847,520 $847,520 $0
https://calsta.ca.gov/ (CalSTA) $5,000,000 $0 $5,000,000
Grand Total $5,847,520 $847,520 $5,000,000

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012 2011 2010 2009
Federal Lands Highway Funding $847,520 $0 $0 $0 $0 $0 $0 $0 $3,920 $28,600 $220,000 $250,000 $120,000 $50,000 $95,000 $80,000
Grand Total $847,520 $0 $0 $0 $0 $0 $0 $0 $3,920 $28,600 $220,000 $250,000 $120,000 $50,000 $95,000 $80,000

Photos

Photos

No photos available.

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
02/28/2023 9:20 AM Judy Weber Project is inactive. Recently applied for calsta.ca.gov/ (CalSTA) grant for $5M.