Conduct hazardous fuel reduction and forest ecosystem health treatments in the Slaughterhouse area on the east shore of the Lake Tahoe Basin. These fuel reduction treatments would cover the National Forest areas and would focus on the Urban Wildland Interface adjacent to the Glenbrook Community and the Highway 28 corridor. Treatments would reduce the level of hazardous fuels within the defense and threat zones. This includes the use of mechanical harvesters and chainsaws for thinning to reduce live tree densities and mechanical chipping to reduce the amount of existing dead and down biomass. Included in project implementation is contract administration and project monitoring. Project

Completed
2006
2008
2010
$1,336,000

Brian Garrett (brian.garrett@usda.gov)
06/01/2014
02/09/2016
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

Organizations

EIP Details

EIP Basics

02.01.01.0044 - Slaughterhouse Healthy Forest Restoration and Fuels Reduction Project
10178

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Acres of Forest Fuels Reduction Treatment
2007 2008 2009 2010 Total Units
Initial or Maintenance Treatment Property Ownership Treatment Type Treatment Zone
Initial U.S. Forest Service Hand Thinning Community Defense Zone 110 110 acres
Initial U.S. Forest Service Mechanical Thinning Community Defense Zone 339 88 427 acres
Initial U.S. Forest Service Prescribed Burning Community Defense Zone 925 925 acres
Total 110 339 88 925 1,462 acres

Funding

Expected Funding

Expected Funding
$1,336,000
$1,336,000
$0

Total
Unknown or Unassigned $1,336,000 $1,336,000 $0
Grand Total $1,336,000 $1,336,000 $0

Reported Expenditures

Reported Expenditures
Total 2010 2009 2008 2007
Southern Nevada Public Land Management Act $1,336,000 $43,000 $377,000 $278,000 $638,000
Grand Total $1,336,000 $43,000 $377,000 $278,000 $638,000

Photos

Photos

No photos available.

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
05/21/2014 6:01 PM System The total project cost is based on 4 rounds (9-12) and 4 projects of SNPLMA funding. Initial fuels reduction and thinning is estimated to be complete at the conclusion of SNPLMA Round 12 funding.