To zoom, hold down the Shift key and drag a rectangle.
|
|
Location Information | Location Notes |
---|---|
|
Tahoe City Public Utility District (TCPUD) | Kim Boyd - Tahoe City Public Utility District (TCPUD) |
No expected performance measures set for this project.
Miles of Roads Decommissioned or Retrofitted | ||||||
---|---|---|---|---|---|---|
|
2018 | 2019 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | ||||
Tahoe City Public Utility District | Paved | Retrofitted | 0.25 | 0.25 | 0.5 | miles |
Total | 0.25 | 0.25 | 0.5 | miles |
Total | |||
---|---|---|---|
Tahoe City Public Utility District (TCPUD) | $136,619 | $136,619 | $0 |
Grand Total | $136,619 | $136,619 | $0 |
Total | 2019 | 2018 | 2017 | 2016 | 2015 | |
---|---|---|---|---|---|---|
Tahoe City Public Utility District | $136,619 | $115,104 | $21,515 | $0 | $0 | $0 |
Grand Total | $136,619 | $115,104 | $21,515 | $0 | $0 | $0 |
No Related Projects set for this project.
No external links entered.
11/26/2019 12:38 PM | Kim Boyd | After full construction of the Bunker water tank in 2018, the access road was paved and BMPs were installed beginning in 2018 and completed in 2019. | ||
12/28/2017 11:19 AM | Kurt Althof | Site work began at the end of 2017. Access Road BMPs did not secure any outside funding. Project expected to be complete in 2018 | ||
05/21/2014 6:01 PM | System | Project is not funded. No work performed during reporting period |