Untreated or under-treated stormwater is being directly discharged to the Lake. The project installed 950' of conveyance pipe to connect 2 highway catchments to a new infiltration basin designed to reduce fine sediment particles, nitrogen and phosphorus delivery to Lake Tahoe. The project also stabilized 2 eroding beach outfalls and provided infiltration where possible.

Completed
2013
2016
2017
$960,705

Meghan Kelly (mkelly@ntcd.org)
06/27/2017
12/27/2017
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Roads Decommissioned or Retrofitted None miles

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2016 2017 Total Units
Property Ownership Road Type Treatment Type
Douglas County Paved Retrofitted 0.1 0.1 miles
Nevada Department of Transportation Paved Retrofitted 0.3 0.3 miles
Total 0.1 0.3 0.4 miles

No accomplishments to report for:
Year(s) 2014, 2015
Explanation Project was in design phase during 2014 and 2015

Funding

Expected Funding

Expected Funding
$960,705
$960,705
$0

Total
Nevada Department of Transportation (NDOT) $390,000 $390,000 $0
Nevada Division of Environmental Protection (NDEP) $105,705 $105,705 $0
Southern Nevada Public Land Management Act (USFS - LTBMU) $315,000 $315,000 $0
Tahoe Bonds Act (NDSL) $150,000 $150,000 $0
Grand Total $960,705 $960,705 $0

Reported Expenditures

Reported Expenditures
Total 2017 2016 2015 2014 2013
Nevada Department of Transportation $390,000 $381,365 $8,635 $0 $0 $0
Nevada Division of Environmental Protection $105,705 $97,018 $8,687 $0 $0 $0
Southern Nevada Public Land Management Act $315,000 $19,783 $40,836 $87,120 $72,492 $94,769
Tahoe Bonds Act $150,000 $0 $135,451 $14,549 $0 $0
Grand Total $960,705 $498,166 $193,609 $101,669 $72,492 $94,769

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes

No notes entered.