Overview

Basics

Basics
Annual Streets and Roads Operations and Maintenance (existing, does not reflect future TMDL implementation) – City of South Lake Tahoe. This includes all on-going, recurring costs for operations and maintenance of roadways including snow removal and abrasives recovery. One-time maintenance is tracked under a different project. Annual operations and maintenance costs must be tracked as part of the Regional Transportation Plan Update.

Implementation
2015
2015
2045

Stan Hill (shill@cityofslt.us)
06/01/2014
01/26/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

Organizations
City of South Lake Tahoe (CSLT) Stan Hill - City of South Lake Tahoe (CSLT)

EIP Details

EIP Basics

01.01.02.0008 - Streets and Roads Operations and Maintenance – City of South Lake Tahoe

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
No
Operations and Maintenance
This project is a Transportation Operations and Maintenance project with recurring annual costs.
$2,600,000
$93,630,441 (For years 2020-2045 using 2.50% annual inflation)

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Miles of Street Sweeping
2015 2016 2017 2018 2019 2020 2021 2022 2023 Total Units
Equipment Type Property Ownership
High-Efficiency Vacuum-Assisted Dry Sweeper City of South Lake Tahoe 256 256 256 256 256 256 256 256 256 2,304 miles
Total 256 256 256 256 256 256 256 256 256 2,304 miles

Funding

Expected Funding

Expected Funding

Expected Funding is not applicable to Transportation O&M projects.

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018 2017 2016 2015
City of South Lake Tahoe General Fund $22,501,436 $3,680,726 $3,680,726 $3,680,726 $1,062,035 $0 $2,527,583 $3,065,848 $2,319,792 $2,484,000
Grand Total $22,501,436 $3,680,726 $3,680,726 $3,680,726 $1,062,035 $0 $2,527,583 $3,065,848 $2,319,792 $2,484,000

Photos

Photos

No photos available.

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
01/24/2022 8:48 AM Randy Carlson Streets Department O&M for 2021 was $1,264,791.
Road Rehabilitation Project cost was $2,415,935.
02/04/2016 9:16 AM Jim Marino 02-04-16 - J.M. The $2,484,000 O&M costs shown reflect both the Operations Program (streets and Roads) and the Snow removal Program (streets and roads). This total does not reflect TMDL measures such as sweeping, Road RAM, abrasives collection etc. Nor does the amount reflect annual pavement rehabilitation projects which are sporadic in funding allocation