Overview

Basics

Basics
Annual Stormwater Treatment Facilities Operations and Maintenance – Washoe County. This includes all on-going, recurring costs for stormwater treatment facilities operations and maintenance.

Implementation
2009
2009
2045

Domi Fellers (dfellers@ntcd.org)
06/01/2014
12/08/2023
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

Organizations
Washoe County, NV (WACO) Dave Solaro - Washoe County, NV (WACO)

EIP Details

EIP Basics

01.01.02.0014 - Stormwater Treatment Facilities Operations and Maintenance – Washoe County

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
No
Operations and Maintenance
This project is a Transportation Operations and Maintenance project with recurring annual costs.
$200,000
$7,202,342 (For years 2020-2045 using 2.50% annual inflation)

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures

No annual performance measure accomplishments entered for this project.


No accomplishments to report for:
Year(s) 2009, 2010, 2011, 2012, 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023
Explanation There are no performance measures for O&M activity on Stormwater Treatment Facilities.

Funding

Expected Funding

Expected Funding

Expected Funding is not applicable to Transportation O&M projects.

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012 2011 2010 2009
Washoe County Road Enterprise Fund $2,249,270 $102,718 $41,874 $68,132 $154,546 $194,500 $153,500 $219,000 $76,500 $202,000 $216,500 $200,000 $180,000 $160,000 $140,000 $140,000
Grand Total $2,249,270 $102,718 $41,874 $68,132 $154,546 $194,500 $153,500 $219,000 $76,500 $202,000 $216,500 $200,000 $180,000 $160,000 $140,000 $140,000

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
12/08/2023 2:53 PM Judy Weber Spoke with NTCD on the est. annual operating cost $200,000.

A new crew leader is taking over and is going to dedicate some resources to performing stormwater facilities maintenance this year. Hold off adjusting and see what next year's total is.

12/04/2023 3:41 PM Domi Fellers 2023 reporting includes expenditures from 10/1/2022 through 9/30/2023. O&M includes AC berm installation and repair, erosion control. ditch cleaning, retention pond cleaning, DI/MH install, cleaning and repair, flood control, pipe installation and cleaning.
12/27/2022 12:54 PM Domi Fellers 2022 reporting includes expenditures from 10/1/2021 through 9/30/2022. O&M includes AC berm installation and repair, erosion control. ditch cleaning, retention pond cleaning, DI/MH install, cleaning and repair, flood control, pipe installation and cleaning. Amount spent during 2022 is most likely low due to staff shortages and a low water year usually equates to less sprint/summer maintenance.
01/05/2022 1:48 PM Domi Fellers 2021 reporting includes expenditures from 10/1/2020 through 9/30/2021. O&M includes AC berm installation and repair, erosion control. ditch cleaning, retention pond cleaning, DI/MH install, cleaning and repair, flood control, pipe installation and cleaning. Amount spent during 2021 is most likely low due to staff shortages and a low water year usually equates to less sprint/summer maintenance.
01/13/2021 10:11 AM Domi Fellers 2020 reporting includes expenditures from 10/1/2019 through 9/30/2020. O&M includes AC berm installation and repair, erosion control. ditch cleaning, retention pond cleaning, DI/MH install, cleaning and repair, flood control, pipe installation and cleaning.
12/23/2019 11:19 AM Ben Jesch 2019 reporting includes expenditures from 10/1/18 thru 9/30/19. In 2019, Washoe County implemented new asset management software and costs were generated from the new system. The update costs are based on the asset hourly cost, which is calculated based on previous years Total Cost of Ownership and hours used. The County will continue to update and revise cost data as the system and processes mature and evolve. (The previous multiplier, $88/ hour, is no longer being used). Note that Indirect Cost Rate (CoCAP) decreased to 16.01% for 2019.
12/17/2018 9:46 AM Ben Jesch 2018 reporting includes expenditures from 10/1/17 thru 9/30/18. Hourly rate estimated at $88/hr, since 2015. Note that Indirect Cost Rate (CoCAP) decreased to 19.03% for 2018.
01/02/2018 5:04 PM Ben Jesch 2017 reporting includes expenditures from 10/1/16 thru 9/30/17. O&M includes AC berm installation and repair, erosion control, ditch cleaning, retention pond cleaning, DI/MH install, cleaning and repair, flood control, pipe installation and cleaning. Cost from Maintstar with multiplier of 1.32 for CoCAP overhead. Hourly rate estimated at $88/hr, based on 2015 total expenditures divided by man hours.
12/30/2016 9:30 AM Kris Klein 2016 Expenditures are lower than previous years due to a 9-month reporting period and more resources being spent on pavement management during the reporting period.
12/28/2016 3:52 PM Ben Jesch Includes expenditures from 1/1/16 thru 9/30/16. O & M includes AC berm installation and repair, DI/MH cleaning and repair, flood control, pipe installation and cleaning. Cost from Maintstar with multiplier of 1.32 for CoCAP overhead. Hourly rate estimated at $88/hr, based on 2015 total expenditures divided by man hours.
01/14/2016 9:51 AM Kimble Corbridge O & M includes AC berm installation and repair, Erosion control, ditch cleaning, DI/MH cleaning and repair, flood control, pipe installation, cleaning and repair. Cost from Maintstar with multiplier of 1.32 for CoCAP overhead.
12/18/2015 11:50 AM Ben Jesch Maintstar report with hours and staff costs were available for 2014 and forward. Previous years are estimated.
12/18/2015 11:46 AM Ben Jesch 2010 Reporting Period - There was 13 cubic yards of material removed from the drop inlets and sediment cans and 51 labor hours and 26 equipment hours for this program.
12/18/2015 11:45 AM Ben Jesch 2009 Reporting Period - There was 81 cubic yards of material removed from the drop inlets and sediment cans and 301 labor hours and 157 equipment hours for this program.