Overview

Basics

Basics
Untreated or under-treated stormwater was being directly discharged to the Lake. Stormwater infrastructure was installed along the US-50 in the NDOT right-of-way and within the Pittman Terrace neighborhood to treat stormwater runoff prior to discharge to the lake. 560 linear feet of infiltration ditch and 290 linear feet of underground infiltration galleries were installed to capture and infiltrate stormwater. The NDOT US-50 catchment was considered a high priority catchment due to its being a high pollutant loading and directly connected catchment in a highly constrained area. Project is registered in the LT Info Stormwater Tools and has the potential to garner NDOT 8 Lake Clarity Credits.

Completed
2016
2018
2018
$528,387

Meghan Kelly (mkelly@ntcd.org)
11/12/2015
01/05/2021
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Roads Decommissioned or Retrofitted None miles

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2018 Total Units
Property Ownership Road Type Treatment Type
Douglas County Paved Retrofitted 0.5 0.5 miles
Nevada Department of Transportation Paved Retrofitted 0.5 0.5 miles
Total 1 1 miles

Funding

Expected Funding

Expected Funding
$528,387
$528,387
$0

Total
319 Funds (USEPA) $127,000 $127,000 $0
Nevada Department of Transportation (NDOT) $242,000 $242,000 $0
Private Property Owners (Private) $25,000 $25,000 $0
Tahoe Bonds Act (NDSL) $134,387 $134,387 $0
Grand Total $528,387 $528,387 $0

Reported Expenditures

Reported Expenditures
Total 2018 2017 2016
Nevada Department of Transportation $242,000 $219,865 $22,135 $0
Nevada Division of Environmental Protection $127,000 $106,515 $15,915 $4,570
Private Property Owners $0 $0 $0 $0
Tahoe Bonds Act $134,387 $120,832 $13,555 $0
Grand Total $503,387 $447,212 $51,605 $4,570

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
01/03/2021 6:17 PM Meghan Kelly $25k from Private property owners was supposed to come from re-paving roads in Pittman Terrace and we are unsure that this has happened.