Overview

Basics

Basics
The project revises the 1980 General Plan for Kings Beach State Recreation Area (KBSRA), expands the KBSRA boundary to include the 1.36-acre Kings Beach Plaza (Plaza), and considers potential land ownership transfer of the Plaza to State Parks. The General Plan revision would provide a comprehensive framework for projects within, and management of, KBSRA over the next 20 years. The project also includes three locational alternatives for rebuilding the Kings Beach pier to a standard that increases its functionality for boating. The preferred pier location is to the east end of KBSRA.

Planning/Design
2016
2024
2026
$5,676,000

Angelique Carl (Angelique.Carl@parks.ca.gov)
05/13/2016
12/20/2023
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.01.02.0099 - Kings Beach Pier Reconstruction

This project is on the EIP 5-year list.

Performance Measures

Expected Performance Measures

Expected Performance Measures
Facilities Improved or Created None number

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$5,676,000
$1,429,666
$4,246,334

Total
California Department of Parks and Recreation (CDPR) $392,000 $392,000 $0
California Tahoe Conservancy (CTC) $500,000 $500,000 $0
North Tahoe Community Alliance (NTCA) $95,000 $95,000 $0
Proposition 84 (CDPR) $442,666 $442,666 $0
Grand Total $1,429,666 $1,429,666 $0

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018 2017 2016
California Department of Parks and Recreation $76,400 $0 $0 $9,500 $4,500 $15,600 $15,600 $15,600 $15,600
California Tahoe Conservancy $525,700 $60,000 $0 $0 $0 $0 $131,700 $167,000 $167,000
California Wildlife Conservation Board $60,000 $60,000 $0 $0 $0 $0 $0 $0 $0
North Tahoe Community Alliance $94,600 $0 $0 $0 $0 $0 $28,600 $33,000 $33,000
Proposition 84 $381,500 $0 $0 $0 $0 $2,500 $79,000 $150,000 $150,000
Grand Total $1,138,200 $120,000 $0 $9,500 $4,500 $18,100 $254,900 $365,600 $365,600

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

  • The Kings Beach Pier Reconstruction project will help maintain recreation threshold attainment status by providing high quality access to Lake Tahoe available to the general public. Reconstructing the public pier at KBSRA so that it functions as lake access during the diversity of lake level conditions will enhance the public’s access to the shorezone and Lake Tahoe.

Local and Regional Plans

Related Projects

Related Projects

03.01.02.0099 - Kings Beach Pier Reconstruction is associated with following groups of projects.

External Links

No external links entered.

Notes

Notes
12/15/2023 2:46 PM Angelique Carl 2023: Exploratory geotechnical investigation is underway with consultants to study bedrock stability for placement of future pier pilings. DPR has draft designs for proposed new pier alignment and improved Day Use facilities - these are being studied along with the development of the KBSRA General Plan.
01/18/2022 10:10 AM Dan Shaw CDPR District Staff working with CDPR Northern Service Center Staff on planning and permits to accommodate exploratory geotechnical investigation to ensure substrate in proposed new pier location is suitable. CDPR anticipates completing the exploratory geotechnical investigation in fall of 2022.
01/14/2021 8:52 PM Courtney Rowe 2020: DPR staff provided continued processing of CTC and WCB grant applications intended to fund PD/WD design of eastern site improvements and pier relocation.
01/03/2020 3:02 PM Ashli Lewis District Staff worked with Parks Acquisitions and Development to prepare a Wildlife Conservation Board Public Access Program Grant application. Grant app made it through pre-application phase into an invitation for a full proposal. Selected projects should be notified this winter.
01/14/2019 10:28 AM Ashli Lewis 1/14/19 – Concept Planning/EIR/EIS is complete however with TRPA permit to be issued first quarter of 2019. No current funding for PP/WD or Construction.
01/12/2018 2:18 PM Dan Shaw The concept Planning/Environmental Review in ongoing.
Cost (secured): $1,040,000 for planning

Preliminary Planning is ongoing and will extend beyond July 2018
05/04/2016 2:44 PM System Concept planning/Environmental review – completed by December 2017
Cost (secured): $245,000

Preliminary Planning – completed by July 2018 (State FY18/19)
Engineering (Working Drawings)/bid – completed by July 2019 (State FY 19/20)
Construction – 2019/2020 (Assume a start of construction after Labor Day to get it out of high use time and MBTA nesting season, so may need two construction seasons)

Cost (unsecured): $3,431,000