To zoom, hold down the Shift key and drag a rectangle.
|
|
Location Information | Location Notes |
---|---|
|
California Department of Forestry and Fire Protection (Cal Fire) | None | |||
California Department of Transportation (Caltrans) | Joan Davis - California Department of Transportation (Caltrans) | |||
California Wildlife Conservation Board (WCB) | None | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
This project is on the EIP 5-year list.
Acres of Forest Fuels Reduction Treatment | None | acres |
Acres of Forest Fuels Reduction Treatment | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
|
2018 | 2019 | 2020 | 2021 | 2022 | 2023 | Total | Units | |||
Initial or Maintenance Treatment | Property Ownership | Treatment Type | Treatment Zone | ||||||||
Initial | U.S. Forest Service | Biomass Removal | Community Defense Zone | 612 | 663 | 0 | 0 | 0 | 1,275 | acres | |
Initial | U.S. Forest Service | Hand Thinning | Community Defense Zone | 0 | 32 | 32 | acres | ||||
Initial | U.S. Forest Service | Mechanical Thinning | Community Defense Zone | 612 | 663 | 0 | 0 | 0 | 1,275 | acres | |
Total | 0 | 1,256 | 1,326 | 0 | 0 | 0 | 2,582 | acres |
Total | |||
---|---|---|---|
California Department of Forestry and Fire Protection (CAL FIRE) (Cal Fire) | $1,430,000 | $1,430,000 | $0 |
California Wildlife Conservation Board (WCB) | $950,000 | $950,000 | $0 |
Lake Tahoe Restoration Act (USFS - LTBMU) | $3,008,000 | $1,408,000 | $1,600,000 |
Southern Nevada Public Land Management Act (USFS - LTBMU) | $4,250,000 | $2,239,750 | $2,010,250 |
U.S. Forest Service (USFS - LTBMU) | $4,070,000 | $4,070,000 | $0 |
Grand Total | $13,708,000 | $10,097,750 | $3,610,250 |
Total | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
California Department of Forestry and Fire Protect... | $631,202 | $0 | $0 | $0 | $631,202 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
California Wildlife Conservation Board | $950,000 | $0 | $0 | $0 | $0 | $0 | $950,000 | $0 | $0 | $0 | $0 | $0 | $0 |
Lake Tahoe Restoration Act | $1,408,000 | $1,408,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Southern Nevada Public Land Management Act | $665,000 | $35,000 | $50,000 | $0 | $0 | $0 | $0 | $0 | $70,000 | $110,000 | $150,000 | $150,000 | $100,000 |
U.S. Forest Service | $3,800,000 | $0 | $225,000 | $25,000 | $1,650,000 | $500,000 | $1,360,000 | $40,000 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $7,454,202 | $1,443,000 | $275,000 | $25,000 | $2,281,202 | $500,000 | $2,310,000 | $40,000 | $70,000 | $110,000 | $150,000 | $150,000 | $100,000 |
No watersheds set for this project.
02.01.01.0089 - Westshore Wildland Urban Interface (WUI) Hazardous Fuels Reduction and Forest Health Project is associated with following groups of projects.
No external links entered.
01/12/2024 4:01 PM | Brian Garrett | Tahoe City WT contract was cancelled. The project is being repackaged into two separate contracts and will be awarded in 2024. Additional funding for anticipated contract cost were added from LTRA funds. Additional field work was needed to finalize Eagle HT contract field layout and was completed in 2023. The contact will now be awarded in 2024. Work did not begin on Tahoe Pines CTL contract, that work will begin in 2024. | ||
01/13/2023 10:14 AM | Brian Garrett | Burton Creek WT mechanical treatment was completed in 2022. Additionally, 309 acres of hand thin acres were field prepped for contact - Eagle Handthin contract is planned to be awarded and begin implementation in 2023. The Tahoe Pines Mechanical contract was not implemented in 2022, but is anticipated to begin implementation in 2023. The Tahoe City WT project was not implemented and is anticipated to begin in 2023. | ||
01/17/2022 6:42 PM | Brian Garrett | The Ward Creek CTL project was completed in FY21, the project was funded by the Calfiornia Wildlife Conservation Board. The Burton Creek WT project awarded in FY20 began and was planned to be completed, however Calfornia Fires and suppression response by the contractor prevented the work to be completed as planned. The project final 68 acres of the project will be completed in FY22. | ||
12/30/2020 10:32 AM | Brian Garrett | Two mechanical contracts awarded in 2020. Burton Creek WT with Calfire CCI grant funding and Tahoe PInes CTL with USFS - LTBMU funding. | ||
01/11/2020 11:28 AM | Brian Garrett | Calfire CCI grant awarded in 2018 to National Forest Foundation for Burton Creek mechanical units 355 acres, updated the expedited expenditures to reflect correct grant amount. | ||
01/11/2020 11:20 AM | Brian Garrett | An additional $500,000 of federal fuels funding spent on project 2019 to complete expired surveys and fund biomass removal. Ward Creek CTL contract awarded and began implementation. | ||
03/04/2019 8:35 PM | Brian Garrett | $360,000 in federal fuels funding secured in 2018 for 1200 acres of mechanical treatment until layout | ||
03/04/2019 8:29 PM | Brian Garrett | Implementation began in 2018, but no units completed, accomplishment will be in 2019. | ||
03/04/2019 8:28 PM | Brian Garrett | $1,000,000 in federal fuels funding secured in 2018 and $950,000 in CA WCB grant funding received via National Forest Foundation partnership, funding spent in 2018 on NFF Stewardship Agreement, acres to be accomplished in 2019 | ||
02/15/2018 2:13 PM | Brian Garrett | Funding updated, USFS - $360 for prep/layout - FY18 USFS RO funding; $200 - FY17 supplemental fuels funding | ||
01/12/2018 8:17 AM | Brian Garrett | Planning was completed in Spring of 2017. Timber Waiver permitting, and some project layout on USFS Urban Forest Parcels included in the project was completed. Agreement with the CCC to implement fuels treatments on USFS lands was completed. GGRF grant funding was received for hand treatment in two small units near Tahoe City. Implementation is planned to begin in FY18. | ||
06/10/2016 2:31 PM | System | This project is in the planning phase, completion of NEPA/decision expected by December 2016. This project is separate from the Tahoe West Collaborative Large Landscape Restoration Project. |