Overview

Basics

Basics
The regional parking management program will utilize advanced technology expansion to display of real-time parking availability information via roadside dynamic message signs, internet applications, and mobile devices for pre-trip planning. Message signs and mobile device applications will provide way-finding guidance to public parking lots to encourage alternative travel modes. Where appropriate, integration of paid parking and regional enforcement strategies will be developed across public and private parking. This includes the VPPP pilot program for paid parking on the East Shore to generate revenues for financing of the Nevada Stateline to Stateline Bikeway.

Completed
2016
2020
2021
$600,000

06/01/2014
05/16/2023
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes
Pilot program is along SR 28 on the East Shore, from Incline Village to Sand Harbor.

Organizations

EIP Details

EIP Basics

04.02.02.0007 - Parking Lot Information and Guidance System Integration/Parking Lot Detection System

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Facilities Improved or Created
2020 Total Units
Action Performed Primary Facility Type Primary Purpose of Facility
Created Miscellaneous Structures Transit 1 1 number
Total 1 1 number

No accomplishments to report for:
Year(s) 2021
Explanation Paid parking began in 2020 and continued in 2021.

Funding

Expected Funding

Expected Funding
$600,000
$441,446
$158,554

Total
AQ Mitigation Funds (TRPA) $115,519 $115,519 $0
Value Pricing Pilot Program (FHWA) $290,455 $290,455 $0
Washoe County Bond (WACO) $35,472 $35,472 $0
Grand Total $441,446 $441,446 $0

Reported Expenditures

Reported Expenditures
Total 2021 2020 2019 2018 2017 2016
AQ Mitigation Funds $115,519 $85,194 $0 $5,738 $23,407 $1,060 $120
Value Pricing Pilot Program $290,455 $40,563 $32,784 $118,770 $93,619 $4,239 $480
Washoe County Bond $35,471 $3,321 $8,196 $23,954 $0 $0 $0
Grand Total $441,445 $129,078 $40,980 $148,462 $117,026 $5,299 $600

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

No Threshold Categories set for this project.

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

Notes

Notes
03/20/2023 2:40 PM Judi Allen The VPPP pilot project grant was completed January 2021. Parking management is still on-going.