Overview

Basics

Basics
Replace existing sander/spreader truck with new truck and Epoke abrasives distribution system. The Epoke system provides control over dispersion of all sanding materials — dry, pre-wet or liquid. Not only preserving the natural environment, but also reducing wasted material and excessive damage to infrastructure (bridges, culverts, etc.). Epoke provides technology to greater control the amount of material used, type of distribution, and area of coverage, using significantly less material while providing a more uniform coverage with just one pass. Utilization of less material results in less materials become airborne, dispersed into storm drains and ultimately reduces recovery time

Completed
2016
2017
2019
$351,563

Stan Hill (shill@cityofslt.us)
07/26/2016
01/25/2021
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes
Non -Infrastructure

Organizations

Organizations
City of South Lake Tahoe (CSLT) Stan Hill - City of South Lake Tahoe (CSLT)

EIP Details

EIP Basics

01.01.01.0170 - Sander Truck upgrade to reduce emissions and abrasives

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2021 2020 2019 2018 2017 2016
City of South Lake Tahoe General Fund (CSLT) $351,563
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0
Construction $351,563 $0 $0 $0 $104,670 $158,596 $88,297
Grand Total $351,563 $0 $0 $0 $104,670 $158,596 $88,297

Performance Measures

Expected Performance Measures

Expected Performance Measures
Pounds of Air Pollutants Removed or Avoided by Project [Pollutant of Concern: Carbon Monoxide (CO)] 350 pounds
Pounds of Air Pollutants Removed or Avoided by Project [Pollutant of Concern: Nitrogen Oxides (NOx)] 42 pounds
Pounds of Air Pollutants Removed or Avoided by Project [Pollutant of Concern: Particulate Matter less than 10 Microns (PM10)] 121 pounds
Pounds of Air Pollutants Removed or Avoided by Project [Pollutant of Concern: Particulate Matter less than 2.5 Microns (PM2.5)] 111 pounds
Tons of Greenhouse Gases Reduced [Type of Mitigation: Avoided Emissions] 0.215 tons

Reported Performance Measures

Reported Performance Measures

No annual performance measure accomplishments entered for this project.


No accomplishments to report for:
Year(s) 2017, 2018, 2019
Explanation purchase of new sander truck does not fit into PMs

Funding

Expected Funding

Expected Funding
$351,563
$351,563
$0

Total
City of South Lake Tahoe General Fund (CSLT) $351,563 $351,563 $0
Grand Total $351,563 $351,563 $0

Reported Expenditures

Reported Expenditures
Total 2019 2018 2017 2016
City of South Lake Tahoe General Fund $351,563 $0 $104,670 $158,596 $88,297
Grand Total $351,563 $0 $104,670 $158,596 $88,297

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

  • 1. Reduction in fine particulate matter resulting from distribution of roadway abrasives. 2. reduction in sweeper recovery operations and emissions resulting from such. 3. CARB 2021 compliant vehicle.
  • Reduction in fine particulates entering storm drain system from distribution of abrasives.

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

Notes

Notes
01/31/2019 9:25 AM Jim Marino 01-31-2019. City will be seeking Buy America Waiver from Caltrans/FHWA during the spring 2019. Buy America Waiver will be required prior to Federal Authorization for purchase.
06/09/2017 8:55 AM Jim Marino 5-22-17 JM - California Tahoe Conservancy is considering exchanging FY CMAQ funds with the City in order to meet delays occurring in the CTC Green-way Trail Project. The City is ok with trading this FY CMAQ allocation for the CTC's 18/19 allocation ($399,000).

06-09-17 JM City has updated this project to reflect the exchange of FY CMAQ funds with CTC to be approved by TRPA and Modified in FTIP.