Location Information | Location Notes |
---|---|
|
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | |||
Washoe County, NV (WACO) | Dave Solaro - Washoe County, NV (WACO) |
This project is on the EIP 5-year list.
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
Miles of Roads Decommissioned or Retrofitted | [Property Ownership: Washoe County], [Road Type: Paved], [Treatment Type: Retrofitted] | miles |
Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.
Total | |||
---|---|---|---|
Lake Tahoe Restoration Act (USFS - LTBMU) | $1,000,000 | $800,000 | $200,000 |
Tahoe Bonds Act (NDSL) | $2,650,000 | $0 | $2,650,000 |
Washoe County General Fund (WACO) | $250,000 | $0 | $250,000 |
WQ Mitigation Funds (TRPA) | $100,000 | $0 | $100,000 |
Grand Total | $4,000,000 | $800,000 | $3,200,000 |
Total | 2023 | |
---|---|---|
Lake Tahoe Restoration Act | $0 | $0 |
Grand Total | $0 | $0 |
No watersheds set for this project.
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
12/01/2023 10:27 AM | Domi Fellers | Washoe County has secured LTRA USFS funding to beginning project scoping and design. The project is still on track for implementation in 2025. | ||
12/05/2022 1:44 PM | Domi Fellers | Project delayed due to Lower Wood Creek Phase 2 prioritization, but planning/permitting should begin in 2023 once funding is secured. Estimated project cost increased from $3.5 million to $4 million due to increased construction costs and inflation. | ||
01/03/2022 3:35 PM | Domi Fellers | Project delayed until 2023 due to Lower Wood Creek Phase 2 prioritization. Estimated project cost remains the same, but could increase by 2025 due to increased construction costs and inflation. | ||
01/21/2021 1:45 PM | Domi Fellers | Project delayed until 2022 due to Lower Wood Creek phase 2 prioritization. Estimated project cost remains the same, but could increase next year due to increasing construction costs and inflation. | ||
01/08/2019 10:38 AM | Ben Jesch | Project delayed until 2022, due to prioritization of Lower Wood Creek Phase II. Estimated project cost increased due to increasing construction costs and inflation due to extended project schedule. |