Location Information | Location Notes |
---|---|
|
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Brent Moore - Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Army Corps of Engineers (USACOE) | None | |||
U.S. Fish and Wildlife Service (USFWS) | Roy Ulibarri - U.S. Fish and Wildlife Service (USFWS) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
Acres Treated for Invasive Species | None | acres | |
Acres of Invasive Species Inventoried | None | acres |
Acres Treated for Invasive Species | ||||||
---|---|---|---|---|---|---|
|
2017 | 2018 | 2019 | 2020 | Total | Units |
Invasive Species Type | ||||||
Aquatic | 4 | 4 | 4 | 4 | 16 | acres |
Total | 4 | 4 | 4 | 4 | 16 | acres |
Acres of Invasive Species Inventoried | ||||||
---|---|---|---|---|---|---|
|
2017 | 2018 | 2019 | 2020 | Total | Units |
Invasive Species Type | ||||||
Aquatic | 22 | 22 | acres | |||
Total | 22 | 0 | 0 | 0 | 22 | acres |
Total | |||
---|---|---|---|
Lake Tahoe License Plate Program (NDSL) | $70,669 | $70,669 | $0 |
Section 108 U.S. Army Corps of Engineers (TRPA) (USACOE) | $80,000 | $80,000 | $0 |
Tahoe Bonds Act (NDSL) | $355,793 | $355,793 | $0 |
Grand Total | $506,462 | $506,462 | $0 |
Total | 2020 | 2019 | 2018 | 2017 | 2016 | |
---|---|---|---|---|---|---|
Lake Tahoe License Plate Program | $192,825 | $0 | $72,557 | $88,500 | $31,768 | $0 |
Lake Tahoe Restoration Act | $28,495 | $28,495 | $0 | $0 | $0 | $0 |
Section 108 U.S. Army Corps of Engineers (TRPA) | $88,883 | $9,426 | $0 | $79,457 | $0 | $0 |
Tahoe Bonds Act | $434,409 | $128,486 | $46,715 | $0 | $259,208 | $0 |
Grand Total | $744,612 | $166,407 | $119,272 | $167,957 | $290,976 | $0 |
No watersheds set for this project.
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
01/21/2021 11:27 AM | Dennis Zabaglo | This projected was completed in 2020. While each year 4 acres were reported as being treated, relocations of barriers each season overlapped some areas from the previous year. In total, aprroximately 9.3 acres were treated. Post-treatment surveys revealed few live clams present with a range of 0-32 live clams present per square meter compared to 0-180 per square meter. See project photos for collected data. |