Although this is a Basin-wide project, the focus will be on west shore of Lake Tahoe associated with Tahoe West Collaborative Restoration.
|
California Natural Resources Agency (CNRA) | Robert Larsen - California Natural Resources Agency (CNRA) | |||
Tahoe Science Advisory Council (TSAC) | Robert Larsen - California Natural Resources Agency (CNRA) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | |||
U.S. Forest Service - Pacific Southwest Research Station (USFS - PSW) | Pat Manley - U.S. Forest Service - Pacific Southwest Research Station (USFS - PSW) |
This project is on the EIP 5-year list.
No expected performance measures set for this project.
No annual performance measure accomplishments entered for this project.
No accomplishments to report for: | |
Year(s) | 2022, 2023 |
---|---|
Explanation | There are no performance measures aligned with research and monitoring accomplishments. |
Total | |||
---|---|---|---|
Southern Nevada Public Land Management Act (USFS - LTBMU) | $400,000 | $400,000 | $0 |
Grand Total | $400,000 | $400,000 | $0 |
Total | 2023 | 2022 | 2021 | |
---|---|---|---|---|
Southern Nevada Public Land Management Act | $100,000 | $50,000 | $50,000 | $0 |
Grand Total | $100,000 | $50,000 | $50,000 | $0 |
No watersheds set for this project.
04.01.01.0038 - Tahoe Environmental Observatory Network is associated with following groups of projects.
No external links entered.
11/01/2023 11:05 AM | Beth Vollmer | Previously titled "Science Support for Management of Landscape Scale Changes on Lake Tahoe" | ||
12/16/2022 9:51 AM | Robert Larsen | SNPLMA funding resurfaced and has been directed to PSW to lead the project. | ||
12/15/2021 11:03 AM | Robert Larsen | Previously secured funding is no longer available. The project will be considered as part of the larger Integrated Science to Action framework and prioritized accordingly. | ||
01/14/2021 1:51 PM | Alan Heyvaert | Project initiation is pending funding transfers, which have been delayed due to process complications that the USFS and BLM have been working to resolve (comm. 1-14-2020 per J. Keely, LTBMU program manager). One year later, funding transfer is still pending LTBMU action (1-14-2021). | ||
01/15/2020 5:00 PM | Alan Heyvaert | SNPLMA funds from BLM will be directed to LTBMU as the federal sponsor on this project for TSAC. |