Overview

Basics

Basics
The Project is the development of a master plan document for the City/County Park known as “56 Acres”. The purpose of the master plan is to develop a comprehensive strategy for the project site, facilities, programs and services that is responsive to the community’s demographics, social background, and recreational and health needs. The plan will serve to guide the City in a wide-ranging future capital implementation plan. Projects resulting from this plan will be separate EIP projects: 1. Rec Center 2. Construction of Through Road (Tallac Avenue to Rufus Allen Blvd) 3. Demolition of existing Rec Center 4. Design and Construction of a new Campground

Completed
2020
2021
2022
$425,000

Jim Marino (jmarino@cityofslt.us)
04/29/2020
02/16/2023
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

Organizations
California Tahoe Conservancy (CTC) Whitney Brennan - California Tahoe Conservancy (CTC)
City of South Lake Tahoe (CSLT) Stan Hill - City of South Lake Tahoe (CSLT)

EIP Details

EIP Basics

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Performance Measures

Expected Performance Measures

Expected Performance Measures
Facilities Improved or Created [Action Performed: Created], [Primary Facility Type: Buildings & Grounds], [Primary Purpose of Facility: Recreation] 60000000 number
Facilities Improved or Created [Action Performed: Improved], [Primary Facility Type: Buildings & Grounds], [Primary Purpose of Facility: Recreation] 1500000 number
Facilities Improved or Created [Action Performed: Created], [Primary Facility Type: Trails & Paths], [Primary Purpose of Facility: Lakefront Access] 10000000 number
Forest Upland Facilities Retrofitted for Stormwater [Ownership: Other], [Type of Retrofit Action: Retrofitted] 3000000 number

Reported Performance Measures

Reported Performance Measures

No annual performance measure accomplishments entered for this project.


No accomplishments to report for:
Year(s) 2021, 2022
Explanation There are no performance measures for this project.

Funding

Expected Funding

Expected Funding
$425,000
$425,000
$0

Total
California Tahoe Conservancy (CTC) $425,000 $425,000 $0
Grand Total $425,000 $425,000 $0

Reported Expenditures

Reported Expenditures
Total 2022 2021 2020
Proposition 68 $439,035 $168,554 $265,446 $5,035
Grand Total $439,035 $168,554 $265,446 $5,035

Photos

Photos

No photos available.

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

  • The purpose of the master plan is to develop a comprehensive strategy for the project site, facilities, programs and services that is responsive to the community’s demographics, social background, and recreational and health needs. The plan will serve to guide the City in a wide-ranging future capital implementation plan in which existing facilities will be modified, new facilities created, storm water improvements, trail improvements and creation, and lake access improvements and creation.
  • Planning - thin Campground canopy
  • Planning - Storm water improvements

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

Notes

Notes
01/09/2023 2:26 PM Jim Marino 01/04/23 - Master Plan is complete.
01/14/2022 8:15 AM Jim Marino As of December 2021, the master planning environmental document and plan were under public review. Estimated completion for the Master Plan document is February 2022