Overview

Basics

Basics
The Tunnel Creek Alternative Trail is a Nevada Division of State Parks project, along with other project partners Nevada Division of State Lands, Tahoe Fund, Great Basin Institute, and TAMBA. It is a 2.28 mile single-track alternative route beginning at the base of the Tunnel Creek canyon with indirect linkage to the Tahoe East Shore Trail and ending with linkage to the south end of the Incline Flume Trail. The need for the trail comes primarily from a desire to address public safety issues between user groups on the very congested Tunnel Creek road. The road is also very sandy and steep, and is responsible for a number of bike accidents every year. The trail will be built in two phases.

Implementation
2018
2022
2024
$400,000

Kevin Fromherz (kfromherz@parks.nv.gov)
01/19/2021
01/09/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.02.02.0091 - Tunnel Creek Alternative Trail

This project is on the EIP 5-year list.

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Trails Developed or Improved [Action Performed: Developed] 3 miles

Reported Performance Measures

Reported Performance Measures
Miles of Trails Developed or Improved
2023 Total Units
Action Performed
Developed 1 1 miles
Total 1 1 miles

No accomplishments to report for:
Year(s) 2022
Explanation Completed the clearances for environmental and historical review. Final plans developed for construction to begin in the summer of 2023.

Funding

Expected Funding

Expected Funding
$400,000
$333,500
$66,500
($180,000 identified as )

Total
Land and Water Conservation Fund (NPS) $180,000 $0 $180,000
Nevada State Parks (NV State Parks) $11,500 $11,500 $0
Recreational Trails Program Funds (FHWA) $72,000 $72,000 $0
Tahoe Bonds Act (NDSL) $200,000 $200,000 $0
Tahoe Fund (Tahoe Fund) $50,000 $50,000 $0
Grand Total $513,500 $333,500 $180,000

Reported Expenditures

Reported Expenditures
Total 2023 2022 2021 2020 2019 2018
Nevada State Parks $3,270 $0 $3,270 $0 $0 $0 $0
Recreational Trails Program Funds $16,186 $16,186 $0 $0 $0 $0 $0
Tahoe Fund $50,424 $45,000 $170 $5,254 $0 $0 $0
TAMBA $18,110 $18,110 $0 $0 $0 $0 $0
Grand Total $87,990 $79,296 $3,440 $5,254 $0 $0 $0

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

  • This project will create a high quality recreational experience for the users of Tunnel Creek area, and provide a safety enhanced addition to the local trail system.

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
01/09/2024 4:38 PM Kevin Fromherz Trail construction began this summer and the first mile of the trail is complete from the state park boundary to the first major switchback of the Tunnel Creek Road. Great Basin institute is funded to complete Phase 1 approximately 1 additional miles. Nevada State Parks is preparing to go to contract for phase 2 this spring and hire a crew to finish the trail. The goal is to complete this project during the summer of 2024.
01/19/2023 4:29 PM Kevin Fromherz Environmental clearances were completed this fall and the project is on track to break ground this summer. Materials for bridges have been purchased and are staged at the project site.
01/06/2022 3:07 PM Jay Howard 2021 expenditure is related to trail brushing that was done in the fall. Full construction is anticipated for spring 2022.