To zoom, hold down the Shift key and drag a rectangle.
|
|
Location Information | Location Notes |
---|---|
|
National Park Service (NPS) | None | |||
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Kevin Fromherz - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | Cassandra Hughes - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
Tahoe Area Mountain Bike Association (TAMBA) | Amy Fish - Tahoe Regional Planning Agency (TRPA) | |||
Tahoe Fund (Tahoe Fund) | Amy Berry - Tahoe Fund (Tahoe Fund) | |||
U.S. Federal Highway Administration (FHWA) | Matt Ambroziak - U.S. Department of Transportation (US DOT) |
This project is on the EIP 5-year list.
Miles of Trails Developed or Improved | [Action Performed: Developed] | 3 | miles |
Miles of Trails Developed or Improved | ||||
---|---|---|---|---|
|
2023 | 2024 | Total | Units |
Action Performed | ||||
Developed | 1 | 0.4 | 1.4 | miles |
Total | 1 | 0.4 | 1.4 | miles |
No accomplishments to report for: | |
Year(s) | 2022 |
---|---|
Explanation | Completed the clearances for environmental and historical review. Final plans developed for construction to begin in the summer of 2023. |
Total | |||
---|---|---|---|
Lake Tahoe License Plate Program (NDSL) | $200,000 | $200,000 | $0 |
Land and Water Conservation Fund (NPS) | $240,000 | $240,000 | $0 |
Nevada State Parks (NV State Parks) | $11,500 | $11,500 | $0 |
Recreational Trails Program Funds (FHWA) | $78,997 | $78,997 | $0 |
Tahoe Fund (Tahoe Fund) | $70,424 | $70,424 | $0 |
Grand Total | $600,921 | $600,921 | $0 |
Total | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | |
---|---|---|---|---|---|---|---|---|
Lake Tahoe License Plate Program | $11,644 | $11,644 | $0 | $0 | $0 | $0 | $0 | $0 |
Land and Water Conservation Fund | $31,854 | $31,854 | $0 | $0 | $0 | $0 | $0 | $0 |
Nevada State Parks | $3,270 | $0 | $0 | $3,270 | $0 | $0 | $0 | $0 |
Recreational Trails Program Funds | $78,997 | $0 | $78,997 | $0 | $0 | $0 | $0 | $0 |
Tahoe Fund | $70,424 | $20,000 | $45,000 | $170 | $5,254 | $0 | $0 | $0 |
TAMBA | $18,110 | $0 | $18,110 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $214,299 | $63,498 | $142,107 | $3,440 | $5,254 | $0 | $0 | $0 |
No watersheds set for this project.
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
12/16/2024 11:41 AM | Cassandra Hughes | Sierra Trail Works was selected to continue the trail construction, breaking ground in late summer 2024, constructing 2,100 feet of the trail. During the winter of 2024/2025, the contractor will be mapping out the second half of the trail. Construction is scheduled to resume in the summer of 2025, with completion anticipated by late summer or early fall 2025. | ||
01/09/2024 4:38 PM | Kevin Fromherz | Trail construction began this summer and the first mile of the trail is complete from the state park boundary to the first major switchback of the Tunnel Creek Road. Great Basin institute is funded to complete Phase 1 approximately 1 additional miles. Nevada State Parks is preparing to go to contract for phase 2 this spring and hire a crew to finish the trail. The goal is to complete this project during the summer of 2024. | ||
01/19/2023 4:29 PM | Kevin Fromherz | Environmental clearances were completed this fall and the project is on track to break ground this summer. Materials for bridges have been purchased and are staged at the project site. | ||
01/06/2022 3:07 PM | Jay Howard | 2021 expenditure is related to trail brushing that was done in the fall. Full construction is anticipated for spring 2022. |