| Location Information | Location Notes |
|---|---|
|
|
|
| Nevada Tahoe Conservation District (NTCD) | Meghan Kelly - Nevada Tahoe Conservation District (NTCD) | |||
| Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Kevin Fromherz - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) |
This project is on the EIP 5-year list.
| Acres of Habitat Restored or Enhanced | [Action Performed: Restored], [Habitat Type: Lake] | 5 | acres |
| Special Status Species Sites Protected or Re-Established | [Action Performed: Protected], [EIP Focal Species: Tahoe Yellow Cress (Rorippa subumbellata)], [Site Type: High-priority ] | 10 | number |
| Disturbed Areas Restored, Enhanced, or Created | None | acres | |
| Forest Upland Facilities Retrofitted for Stormwater | None | number |
| Disturbed Areas Restored, Enhanced, or Created | |||||||
|---|---|---|---|---|---|---|---|
|
|
2021 | 2022 | 2023 | 2024 | Total | Units | |
| Disturbed Area Treatment Type | Ownership | ||||||
| Enhanced | Other | 0.62 | 0.62 | 1.24 | acres | ||
| Restored | Other | 0.57 | 0.62 | 1.19 | acres | ||
| Total | 0.57 | 0.62 | 0.62 | 0.62 | 2.43 | acres | |
| Total | |||
|---|---|---|---|
| Nevada Division of State Lands (NDSL) | $60,000 | $60,000 | $0 |
| Tahoe Bonds Act (NDSL) | $105,186 | $105,186 | $0 |
| Grand Total | $165,186 | $165,186 | $0 |
| Total | 2025 | 2024 | 2023 | 2022 | 2021 | |
|---|---|---|---|---|---|---|
| Nevada Division of State Lands | $27,987 | $0 | $27,987 | $0 | $0 | $0 |
| Tahoe Bonds Act | $105,156 | $0 | $5,690 | $14,945 | $11,993 | $72,528 |
| Grand Total | $133,143 | $0 | $33,677 | $14,945 | $11,993 | $72,528 |
No watersheds set for this project.
01.01.01.0201 - Cave Rock Water Quality Improvement Project is associated with following groups of projects.
No external links entered.
| 12/17/2024 9:50 AM | Christopher LaCasse | 518 feet of permanent fence installed on western side of southern beach in Cave Rock State Park. When NDOT 3R project begins in Summer of 2025/2026, the eastern portion of the fence will be completed, enclosing and protecting the entire eroding hillside. | ||
| 02/29/2024 4:14 PM | Beth Vollmer | 2022: 0.62 acres of hillside repaired, installation of rip rap and new culvert. heavy equipment-based. 2023: 0.62 acres of vegetation, soil mats, protective temporary fencing, and paid for irrigation during the summer season. |
||
| 01/25/2024 2:40 PM | Christopher LaCasse | Permitting is being coordinated with NDOT for their construction of a guardrail, which must be in place prior to or concurrently with the perimeter fence protecting the hillside. A fencing contractor will be secured and project is targeted for completion at the end of summer 2024. | ||
| 12/12/2022 10:31 AM | Christopher LaCasse | Project has been modified to coincide permanent fence installation with NDOT's planned "3 R's" project, which will allow a guardrail on Highway 50 to be installed adjacent to the new fence. |