Overview

Basics

Basics
Van Sickle Phase 3 is an improvement to the Van Sickle Bi-State Park Phase 1. Nevada State Parks has hired a contractor to design a visitor center, improved parking, and restrooms. The visitor center will include park offices, a gift shop, and interpretive spaces. A multi-use paved path is being planned from the visitor to the center to the state border. The planning team is coordinating occurring with California Tahoe Conservancy to continue the path to Lakeview Parkway. An improved monument is being planned for the Nevada/California Stateline that will include additional interpretive opportunities. Construction is tentatively planned for the summer of 2025.

Planning/Design
2022
2025
2026
$20,000,000

Kevin Fromherz (kfromherz@parks.nv.gov)
01/27/2022
02/07/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes
Van Sickle Bi-State Park lower developed area.

Organizations

EIP Details

EIP Basics

03.01.02.0123 - Van Sickle Bi-State Park Phase 3

This project is on the EIP 5-year list.

Performance Measures

Expected Performance Measures

Expected Performance Measures
Facilities Improved or Created None number

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$20,000,000
$950,000
$19,050,000
($6,050,000 identified as )

Total
Land and Water Conservation Fund (NPS) $1,362,500 $0 $1,362,500
Tahoe Bonds Act (NDSL) $5,637,500 $950,000 $4,687,500
Grand Total $7,000,000 $950,000 $6,050,000

Reported Expenditures

Reported Expenditures
Total 2023 2022
Tahoe Bonds Act $288,763 $259,813 $28,950
Grand Total $288,763 $259,813 $28,950

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

  • The construction of Van Sickle Bi-State Park will greatly enhance the recreational experience in the Lake Tahoe basin.

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

03.01.02.0123 - Van Sickle Bi-State Park Phase 3 is associated with following groups of projects.

External Links

No external links entered.

Notes

Notes
01/16/2024 12:00 PM Kevin Fromherz During 2023 the planning team completed a visitor forecast study to estimate visitation through 2048. The design team reworked the plans to ensure the site was able to handle anticipated visitation during 2048. In December 2023 the 30% design was completed and is in the review phase. A new contract is being routed for plans to 100%. Plans are to still break ground during the summer of 2025.
01/19/2023 4:09 PM Kevin Fromherz Park's planning team is working with the contractor on the development concept for phase 3. The current contract takes the plans to 30%.