To zoom, hold down the Shift key and drag a rectangle.
|
|
Location Information | Location Notes |
---|---|
NV Energy transmission and distribution lines
|
Nevada Energy (NV Energy) | Kevin Lawson - Nevada Energy (NV Energy) |
This project is on the EIP 5-year list.
Acres of Forest Fuels Reduction Treatment | None | acres | |
Acres of Forest Fuels Reduction Treatment | [Initial or Maintenance Treatment: Initial], [Property Ownership: Nevada Division of State Lands], [Treatment Type: Mechanical Thinning], [Treatment Zone: Threat Zone] | 2000 | acres |
Acres of Forest Fuels Reduction Treatment | [Initial or Maintenance Treatment: Initial], [Property Ownership: Local public lands (fire districts, counties, GIDs, PUDs, etc.)], [Treatment Type: Mechanical Thinning], [Treatment Zone: Threat Zone] | 2000 | acres |
Acres of Forest Fuels Reduction Treatment | |||||||
---|---|---|---|---|---|---|---|
|
2022 | 2023 | Total | Units | |||
Initial or Maintenance Treatment | Property Ownership | Treatment Type | Treatment Zone | ||||
Initial | Local public lands (fire districts, counties, GIDs, PUDs, etc.) | Mechanical Thinning | Threat Zone | 140 | 108 | 248 | acres |
Initial | Local public lands (fire districts, counties, GIDs, PUDs, etc.) | Prescribed Burning | Threat Zone | 24 | 24 | acres | |
Initial | Nevada Division of State Lands | Mechanical Thinning | Threat Zone | 140 | 108 | 248 | acres |
Initial | Nevada Division of State Lands | Prescribed Burning | Threat Zone | 24 | 24 | acres | |
Total | 280 | 264 | 544 | acres |
No funding sources identified for this project.
Total | 2023 | 2022 | |
---|---|---|---|
Nevada Energy | $600,000 | $300,000 | $300,000 |
Grand Total | $600,000 | $300,000 | $300,000 |
No watersheds set for this project.
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
01/26/2024 9:09 AM | Beth Vollmer | The split is not likely exactly 50/50, but wanted to reflect that some work was on state lands and some on private. reporting for specific land ownership will be dialed in future years. | ||
01/24/2024 10:47 PM | Nanette Hansel | In 2023, the following NDDP system hardening actions were taken that do not have specified performance measures: - 249 single pole replacements - 72 tree attachment removals - 1.3 miles of copper wire was removed and rebuilt with covered conductor (with this rebuild 37 poles were removed and replaced) - Through the partnership with Glenbrook Underground about 0.3 mile of overhead wire was undergrounded. This was not along a scenic travel route so not identified as a separate performance measure. |
||
04/03/2023 11:49 AM | Nanette Hansel | In 2022, the following additional NDPP actions were taken that do not have specified performance measures: - 264 pole replacements - 2.8 miles of copper wire removed - Six tree attachments were removed - Perimeter hardening was completed around the Kingsbury substation |
||
03/05/2023 10:36 PM | Nanette Hansel | The resilience corridors project is designed to treat the areas adjacent to the powerline in three zones as follows: • Zone 1 (up to 15 feet on each side of the power line for 60 kV lines, and up to 21 feet for 120 kV lines): Remove all vegetation, including all trees, within the specified distance (15 or 21 feet) from power poles and create a noncontiguous fuel pattern consistent with the International Wildland Urban Interface Code and NV Energy’s NDPP. • Zone 2 (between 15 and 175 feet on each side of the power line for 60 kV lines, and between 21 and 75 feet for 120 kV lines): Remove trees with structural defects that have the potential to strike utility infrastructure, reduce fuels, and thin to desired conditions. • Zone 3 (between 175 and approximately 1,000 feet on each side of the power line): Reduce fuel loads and thin the forest to desired conditions. Treatments will be accomplished using hand crews and mechanical equipment. Acreages and costs provided are estimates at this time. NDPP infrastructure improvements are intended to ruggedize the system and include replacing copper wire, replacing poles and fuses, and undergrounding overhead distribution lines. System hardening activities include installing non-expulsion fuses, replacing wood poles with ductile iron poles, installing fire retardant pole wrap on wood poles, and other proactive devices. |