Location Information | Location Notes |
---|---|
|
California Tahoe Conservancy (CTC) | Whitney Brennan - California Tahoe Conservancy (CTC) | |||
El Dorado County, CA (ELDO) | Donaldo Palaroan - El Dorado County, CA (ELDO) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
Miles of Roads Decommissioned or Retrofitted | [Property Ownership: El Dorado County], [Road Type: Paved], [Treatment Type: Retrofitted] | 1.3 | miles |
Miles of Street Sweeping | [Equipment Type: High-Efficiency Vacuum-Assisted Dry Sweeper], [Property Ownership: El Dorado County] | 1.3 | miles |
Miles of Pedestrian and Bicycle Routes Improved or Constructed | [Action Performed: Constructed], [Path or Route Type: Class I/Shared Use Path] | 0.9 | miles |
No annual performance measure accomplishments entered for this project.
No accomplishments to report for: | |
Year(s) | 2015, 2016, 2017 |
---|---|
Explanation | See Lake Tahoe Boulevard Erosion Control Project (#01.01.01.0024) for reported PMs. |
Total | |||
---|---|---|---|
Unknown or Unassigned | $570,265 | $570,265 | $0 |
Grand Total | $570,265 | $570,265 | $0 |
Total | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
AQ Mitigation Funds | $17,781 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $9,967 | $0 | $7,814 | $0 |
California Tahoe Conservancy | $40,578 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $5,308 | $0 | $7,628 | $27,642 |
SEZ Mitigation Funds | $24,855 | $0 | $255 | $18,980 | $0 | $0 | $0 | $0 | $0 | $5,620 | $0 | $0 |
Southern Nevada Public Land Management Act | $67,156 | $0 | $0 | $2,471 | $58,155 | $3,396 | $2,786 | $348 | $0 | $0 | $0 | $0 |
Grand Total | $150,370 | $0 | $255 | $21,451 | $58,155 | $3,396 | $2,786 | $348 | $15,275 | $5,620 | $15,442 | $27,642 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
No external links entered.
01/05/2018 9:00 AM | Donaldo Palaroan | Performance measures reported on Lake Tahoe Boulevard Erosion Control Project (#01.01.01.0024). | ||
10/22/2015 12:27 PM | Donaldo Palaroan | Please disregard Performance Measures for this project as this was combined with the Lake Tahoe Boulevard Erosion Control Project (#01.01.01.0024); complete PMs will be reported on that project. | ||
02/03/2015 1:46 PM | Jeanne McNamara | Performance measures for this project for SEZ restoration may have already been counted as completed during the 10-Year EIP reporting in 2006. Need to verify acreage was not previously counted. Also, the expected coverage removal in order to be reported when completed must be permanently retired and cannot be banked in order to be reported. |