Overview

Basics

Basics
The Rocky Point Erosion Control Project was completed in 2012, although the majority of project improvements were constructed in 2008. Improvements include curb and gutter, storm drain pipes, drainage swales, infiltration features/channels and numerous storm water treatment basins in the upper catchment. Runoff in the lower catchment is collected at the Wildwood Wet Basin where significant treatment takes place.

Completed
2012
$6,006,066

Stan Hill (shill@cityofslt.us)
06/01/2014
10/01/2015
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

01.01.01.0027 - Rocky Point Erosion Control Project
695.2

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2010 Total Units
Property Ownership Road Type Treatment Type
City of South Lake Tahoe Paved Retrofitted 4.2 4.2 miles
Total 4.2 4.2 miles
Miles of Street Sweeping
2010 Total Units
Equipment Type Property Ownership
High-Efficiency Vacuum-Assisted Dry Sweeper City of South Lake Tahoe 4.2 4.2 miles
Total 4.2 4.2 miles

Funding

Expected Funding

Expected Funding
$6,006,066
$6,006,066
$0

Total
Unknown or Unassigned $6,006,066 $6,006,066 $0
Grand Total $6,006,066 $6,006,066 $0

Reported Expenditures

Reported Expenditures
Total 2013 2012 2011 2010 2009 2008 2007
California Tahoe Conservancy $1,600,223 $108,630 $3,200 $181,965 $0 $0 $6,763 $1,299,665
Southern Nevada Public Land Management Act $4,405,843 $0 $1,080,465 $39,500 $29,142 $38,414 $2,573,050 $645,272
Grand Total $6,006,066 $108,630 $1,083,665 $221,465 $29,142 $38,414 $2,579,813 $1,944,937

Photos

Photos

No photos available.

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
05/21/2014 6:02 PM System Phase 3 & 4 are completed. Adaptive management is scheduled for 2011
05/21/2014 6:01 PM System Rocky Point ECP Phase 3 and 4