Drainage conveyance stabilization, revegetation, road runoff treatment, and pavement of unpaved roadways in Kings Beach. This project was implemented through different phases including the Coon Street Clean Water Pipe, the Lower Chipmunk Project, and the Lower Secline Project. The Lower Secline project was completed in 2023 and included the paving of Lower Secline and Brockway Vista Ave which were unpaved or in poor condition in close proximity to the lake. The project included paving the existing dirt roads, stabilizing road shoulders, formalizing parking on unimproved surfaces and installing water quality improvements to reduce the quantity of sediment transport.

Implementation
2007
2015
2026
$8,662,710

Andy Deinken (adeinken@placer.ca.gov)
06/01/2014
12/26/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

01.01.01.0045 - Kings Beach Watershed Improvement Project

This project is on the EIP 5-year list.

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

Benefit Category Question
Answer
Score
Questionnaire Score: 6

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2015 2016 2023 Total Units
Property Ownership Road Type Treatment Type
Placer County Paved Retrofitted 0.5 0.25 0.75 miles
Total 0 0.5 0.25 0.75 miles
Linear Feet of Stream Channel Restored or Enhanced
2015 2016 2023 Total Units
Action Performed Watershed
Enhanced Kings Beach 1,534 1,534 linear feet
Total 1,534 0 0 1,534 linear feet
Acres of SEZ Restored or Enhanced
2015 2016 2023 Total Units
Action Performed
Enhanced 0.5 0.5 acres
Total 0.5 0 0 0.5 acres

No accomplishments to report for:
Year(s) 2017, 2018, 2019, 2020, 2021, 2022, 2024
Explanation No PMs to report. Redesign required due to community input. Additional funding needed to be secured to rebid the project for 2023 implementation.

Funding

Expected Funding

Expected Funding
$8,662,710
$10,803,891
($2,141,181)

Total
California Department of Water Resources (California DWR) $2,270,367 $2,270,367 $0
North Tahoe Community Alliance (NTCA) $760,532 $760,532 $0
Placer County General Fund (PLCO) $1,520,000 $1,520,000 $0
SHOPP Funds (Caltrans) $45,000 $45,000 $0
Southern Nevada Public Land Management Act (USFS - LTBMU) $2,671,494 $2,671,494 $0
STIP Funds (Caltrans) $1,254,609 $1,254,609 $0
Stormwater Fee (TRPA) $500,000 $500,000 $0
U.S. Forest Service (USFS - LTBMU) $1,400,000 $1,400,000 $0
WQ Mitigation Funds (TRPA) $381,889 $381,889 $0
Grand Total $10,803,891 $10,803,891 $0

Reported Expenditures

Reported Expenditures
Total 2024 2023 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012 2011 2010 2009 2008 2007
California Department of Water Resources $2,270,367 $0 $0 $0 $0 $0 $0 $0 $0 $1,070,367 $0 $1,200,000 $0 $0 $0 $0 $0 $0 $0
North Tahoe Community Alliance $760,532 $0 $0 $0 $0 $0 $0 $0 $600,000 $0 $160,532 $0 $0 $0 $0 $0 $0 $0 $0
Placer County General Fund $1,520,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,520,000 $0 $0 $0 $0 $0 $0 $0 $0
SHOPP Funds $45,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $45,000 $0 $0 $0 $0 $0 $0 $0 $0
Southern Nevada Public Land Management Act $2,671,494 $0 $401,377 $100,000 $100,000 $100,000 $0 $0 $200,000 $0 $0 $900,000 $560,000 $0 $0 $56,142 $0 $253,975 $0
STIP Funds $1,254,609 $0 $0 $0 $0 $0 $0 $0 $0 $400,000 $854,609 $0 $0 $0 $0 $0 $0 $0 $0
WQ Mitigation Funds $381,889 $0 $339,804 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $42,085
Grand Total $8,903,891 $0 $741,181 $100,000 $100,000 $100,000 $0 $0 $800,000 $1,470,367 $2,580,141 $2,100,000 $560,000 $0 $0 $56,142 $0 $253,975 $42,085

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

Notes

Notes
12/06/2024 4:12 PM Kevin Shifflet Lower Secline Water Quality Improvement Project completed fall 2023.