California Department of Transportation (Caltrans) | Joan Davis - California Department of Transportation (Caltrans) | |||
North Tahoe Community Alliance (NTCA) | None | |||
Placer County, CA (PLCO) | Kansas McGahan - Placer County, CA (PLCO) | |||
Truckee Tahoe Airport District (TTAD) | None | |||
U.S. Federal Transit Administration (FTA) | None | |||
Washoe County, NV (WACO) | Dave Solaro - Washoe County, NV (WACO) |
This project is on the EIP 5-year list.
Total | 2026 | 2025 | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
FTA 5307 (Capital) (FTA) | $3,175,677 | |||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $3,175,677 | $408,006 | $408,006 | $408,006 | $1,543,653 | $408,006 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
FTA 5310 Enhanced Mobility for Elderly and Disabled (FTA) | $190,660 | |||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $190,660 | $64,333 | $0 | $64,333 | $0 | $61,994 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
FTA 5339 Bus and Bus Facility Program (FTA) | $835,191 | |||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $835,191 | $173,173 | $173,173 | $157,836 | $157,836 | $173,173 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
LCTOP - (Low Carbon Transit Operations Program) (Caltrans) | $724,012 | |||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $724,012 | $0 | $117,006 | $0 | $280,000 | $0 | $117,006 | $0 | $210,000 | $0 | $0 | $0 | $0 | |
Placer County Transient Occupancy Tax (PLCO) | $2,525,000 | |||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $2,525,000 | $505,000 | $505,000 | $505,000 | $505,000 | $505,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
TDA-STA (Caltrans) | $1,826,697 | |||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $1,826,697 | $220,000 | $220,000 | $220,000 | $719,437 | $447,260 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Grand Total | $9,277,237 | $1,370,512 | $1,423,185 | $1,355,175 | $3,205,926 | $1,595,433 | $117,006 | $0 | $210,000 | $0 | $0 | $0 | $0 |
No expected performance measures set for this project.
No annual performance measure accomplishments entered for this project.
No accomplishments to report for: | |
Year(s) | 2017, 2018, 2019, 2020, 2021, 2022, 2023 |
---|---|
Explanation | 215,721 vehicle service miles and 11,138 vehicle service hours in enhanced TART service added with Placer County TOT funding |
Total | |||
---|---|---|---|
FTA 5307 (Capital) (FTA) | $3,175,677 | $3,175,677 | $0 |
FTA 5310 Enhanced Mobility for Elderly and Disabled (FTA) | $190,660 | $190,660 | $0 |
FTA 5339 Bus and Bus Facility Program (FTA) | $835,191 | $835,191 | $0 |
LCTOP - (Low Carbon Transit Operations Program) (Caltrans) | $724,012 | $724,012 | $0 |
Placer County Transient Occupancy Tax (PLCO) | $2,525,000 | $2,525,000 | $0 |
TDA-STA (Caltrans) | $1,826,697 | $1,826,697 | $0 |
Grand Total | $9,277,237 | $9,277,237 | $0 |
Total | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | |
---|---|---|---|---|---|---|---|---|---|---|
FTA 5307 (Capital) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
FTA 5310 Enhanced Mobility for Elderly and Disable... | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
FTA 5339 Bus and Bus Facility Program | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
LCTOP - (Low Carbon Transit Operations Program) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Placer County Transient Occupancy Tax | $300,000 | $0 | $0 | $0 | $0 | $0 | $100,000 | $100,000 | $100,000 | $0 |
TDA-STA | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $300,000 | $0 | $0 | $0 | $0 | $0 | $100,000 | $100,000 | $100,000 | $0 |
No watersheds set for this project.
No Related Projects set for this project.
No external links entered.
01/23/2019 8:48 AM | Morgan Beryl | Dollar Hill Bus Shelter constructed in 2018 for $80,000. |