Overview

Basics

Basics
Intersection improvements to provide for improved pedestrian safety and circulation at SR28 and Grove St. in Tahoe City, including potential signalization and accessibility upgrades.

Planning/Design
2021
2026
2028
$2,125,000

Andy Deinken (adeinken@placer.ca.gov)
12/21/2016
03/02/2026
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

Organizations

EIP Details

EIP Basics

03.02.01.0024 - Tahoe City Complete Streets Highway Improvements

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2028 2027 2026 2025 2024 2023 2022 2021 2020 2019 2018
Placer County General Fund (PLCO) $500,000
Preliminary Engineering $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Placer County Transient Occupancy Tax (PLCO) $13,624
Preliminary Engineering $13,624 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,624
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $1,779,000
Preliminary Engineering $379,000 $0 $0 $125,000 $0 $0 $0 $254,000 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $1,400,000 $0 $1,400,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grand Total $2,292,624 $0 $1,400,000 $125,000 $0 $0 $0 $254,000 $0 $0 $0 $513,624

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$2,125,000
$2,292,624
($167,624)
($350,000 identified as )

Total
Placer County General Fund (PLCO) $500,000 $500,000 $0
Placer County Transient Occupancy Tax (PLCO) $363,624 $13,624 $350,000
Surface Transportation Block Grant (STBG) - California (FHWA) $1,779,000 $1,779,000 $0
Grand Total $2,642,624 $2,292,624 $350,000

Reported Expenditures

Reported Expenditures
Total 2025 2024 2023 2022 2021
Placer County General Fund $165,388 $97,315 $3,474 $36,332 $28,267 $0
Placer County Transient Occupancy Tax $13,624 $0 $0 $0 $0 $13,624
Surface Transportation Block Grant (STBG) - Califo... $397,107 $231,349 $10,421 $108,997 $46,340 $0
Grand Total $576,119 $328,664 $13,895 $145,329 $74,607 $13,624

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

03.02.01.0024 - Tahoe City Complete Streets Highway Improvements is associated with following groups of projects.

External Links

Notes

Notes
01/21/2026 2:57 PM Judy Weber SHOPP Project 4643 - On SR 28, in Tahoe City, from 0.1 mile west to 0.1 mile east of Grove Street (PM 0.4/0.6). Install new traffic signals. Financial Contribution Only (FCO) $2650,000 to Placer County. (EA-0N340).
12/19/2024 3:37 PM Judy Weber FTIP project name: Tahoe City Mobility – Grove Street Intersection Improvements
11/07/2024 5:45 PM Andy Deinken Project description and funding have been refined to reflect the current project scope, which mainly entails improvements for pedestrian access and safety at the SR28/Grove Street intersection. Prior expenditures which were not associated with the current scope have been removed.
01/11/2023 12:12 PM Ryan Decker Funding shifted to correct previous errors when separating overall "Tahoe City Mobility" project into three separate projects (TC Complete Streets, TC Mobility, and Lakeside Trail). Coordination with Caltrans on Grove Street intersection improvements ongoing and causing delays in implementation.
12/12/2016 3:39 PM Lucia Maloney Previously called: Tahoe City Traffic Management Program.