Overview

Basics

Basics
Bike trail, lighting and landscaping rehabilitation along Linear Park. Project improvements include reconstruction of an existing Class 1 bike trail, the addition of street lights, and landscaping with an irrigation system.

Completed
2012
2013
$838,000

Stan Hill (shill@cityofslt.us)
06/01/2014
07/22/2015
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.02.02.0020 - Class I Bike Trail - Linear Park Rehabilitation

Transportation Details

Transportation Basics

Transportation Basics
No
Capital

Estimated Budgets

Estimated Budgets

No budgets have been entered for this project.

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Miles of Pedestrian and Bicycle Routes Improved or Constructed
2013 Total Units
Action Performed Path or Route Type
Improved Class I/Shared Use Path 0.32 0.32 miles
Total 0.32 0.32 miles

No accomplishments to report for:
Year(s) 2012, 2014, 2015
Explanation Project construction was completed in 2013. Project work involved the reconstruction of an existing Class 1 bike trail with new added street lighting and landscaping.

Funding

Expected Funding

Expected Funding
$838,000
$838,000
$0

Total
Unknown or Unassigned $838,000 $838,000 $0
Grand Total $838,000 $838,000 $0

Reported Expenditures

Reported Expenditures
Total 2013 2012
City of South Lake Tahoe General Fund $318,571 $0 $318,571
Commercial Property Owners $22,000 $0 $22,000
SHOPP Funds $222,570 $0 $222,570
STIP Funds $275,074 $0 $275,074
Grand Total $838,215 $0 $838,215

Photos

Photos

No photos available.

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
01/05/2015 1:23 PM Stan Hill Linear Park Rehabilitation Project construction was completed during the summer of 2013. Project improvements included reconstruction of an existing Class 1 bike trail, the addition of street lights, and landscaping with an irrigation system.