Location Information | Location Notes |
---|---|
|
Incline Village General Improvement District (IVGID) | HUDSON KLEIN - Incline Village General Improvement District (IVGID) | |||
Nevada Department of Transportation (NDOT) | Chris Holman - Nevada Department of Transportation (NDOT) | |||
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Brent Moore - Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | |||
Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | Kevin Fromherz - Nevada Tahoe Resource Team – Nevada Division of State Parks (NV State Parks) | |||
Tahoe Fund (Tahoe Fund) | Amy Berry - Tahoe Fund (Tahoe Fund) | |||
U.S. Federal Highway Administration (FHWA) | Matt Ambroziak - U.S. Department of Transportation (US DOT) | |||
Washoe County, NV (WACO) | Dave Solaro - Washoe County, NV (WACO) |
The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).
Total | 2020 | 2019 | 2018 | 2017 | 2016 | ||
---|---|---|---|---|---|---|---|
Federal Lands Access Program (FLAP) (FHWA) | $11,568,000 | ||||||
Preliminary Engineering | $11,568,000 | $0 | $0 | $0 | $11,568,000 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $0 | $0 | $0 | $0 | $0 | $0 | |
Nevada Department of Transportation (NDOT) | $6,405,000 | ||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $6,405,000 | $0 | $0 | $0 | $6,405,000 | $0 | |
Nevada State Gas Tax (NDOT) | $20,027,000 | ||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $20,027,000 | $0 | $0 | $0 | $20,027,000 | $0 | |
Grand Total | $38,000,000 | $0 | $0 | $0 | $38,000,000 | $0 |
Miles of Roads Decommissioned or Retrofitted | None | miles | |
Miles of Pedestrian and Bicycle Routes Improved or Constructed | None | miles | |
Pounds of Air Pollutants Removed or Avoided by Project | None | pounds |
Miles of Pedestrian and Bicycle Routes Improved or Constructed | ||||
---|---|---|---|---|
|
2019 | Total | Units | |
Action Performed | Path or Route Type | |||
Constructed | Class I/Shared Use Path | 3 | 3 | miles |
Total | 3 | 3 | miles |
No accomplishments to report for: | |
Year(s) | 2016, 2017, 2018, 2020 |
---|---|
Explanation | In implementation phase. Accomplishments reported for 2019. |
Total | |||
---|---|---|---|
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) | $114,528 | $114,528 | $0 |
Federal Lands Access Program (FLAP) (FHWA) | $11,568,000 | $11,568,000 | $0 |
Incline Village General Improvement District (IVGID) | $1,102,600 | $1,102,600 | $0 |
National Scenic Byways Program Funds (FHWA) | $2,000,000 | $2,000,000 | $0 |
Nevada Recreational Trails Grant (NV State Parks) | $148,570 | $148,570 | $0 |
Nevada State Gas Tax (NDOT) | $34,543,832 | $34,543,832 | $0 |
Question 1 (NDSL) | $2,317,731 | $2,317,731 | $0 |
Tahoe Fund (Tahoe Fund) | $420,000 | $420,000 | $0 |
Washoe County General Fund (WACO) | $1,000,000 | $1,000,000 | $0 |
Grand Total | $53,215,261 | $53,215,261 | $0 |
Total | 2020 | 2019 | 2018 | 2017 | 2016 | |
---|---|---|---|---|---|---|
Congestion Mitigation and Air Quality Program (CMA... | $106,024 | $0 | $12,975 | $46,635 | $46,414 | $0 |
Federal Lands Access Program (FLAP) | $11,463,404 | $0 | $2,080,493 | $3,157,810 | $3,356,553 | $2,868,548 |
Incline Village General Improvement District | $1,014,509 | $0 | $147,572 | $420,098 | $446,839 | $0 |
National Scenic Byways Program Funds | $1,799,288 | $0 | $226,756 | $762,013 | $810,519 | $0 |
Nevada Recreational Trails Grant | $133,646 | $0 | $16,831 | $56,606 | $60,209 | $0 |
Nevada State Gas Tax | $33,051,692 | $340,674 | $4,002,959 | $10,030,382 | $12,765,092 | $5,912,585 |
Question 1 | $2,084,924 | $0 | $262,572 | $883,070 | $939,282 | $0 |
Tahoe Fund | $377,812 | $0 | $47,581 | $160,022 | $170,209 | $0 |
Washoe County General Fund | $899,553 | $0 | $113,288 | $381,006 | $405,259 | $0 |
Grand Total | $50,930,852 | $340,674 | $6,911,027 | $15,897,642 | $19,000,376 | $8,781,133 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
04/14/2021 11:31 AM | Beth Vollmer | Water quality improvements don't fit into PMs | ||
07/11/2018 5:45 PM | Matt Nussbaumer | Use the Photos Link in the External Links for this project to view the project photo gallery. |