Location Information | Location Notes |
---|---|
|
California Department of Transportation (Caltrans) | Joan Davis - California Department of Transportation (Caltrans) | |||
California Tahoe Conservancy (CTC) | Whitney Brennan - California Tahoe Conservancy (CTC) | |||
City of South Lake Tahoe (CSLT) | Stan Hill - City of South Lake Tahoe (CSLT) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Federal Highway Administration (FHWA) | Matt Ambroziak - U.S. Department of Transportation (US DOT) |
Total | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 | 2005 | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
AQ Mitigation Funds (TRPA) | $260,419 | ||||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $260,419 | $0 | $260,419 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Caltrans DEMO Funds (FHWA) | $1,655,000 | ||||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $685,000 | $0 | $0 | $0 | $0 | $685,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $970,000 | $970,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
City of South Lake Tahoe General Fund (CSLT) | $777,500 | ||||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $10,000 | $0 | $10,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $767,500 | $0 | $767,500 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) | $710,000 | ||||||||||||||
Preliminary Engineering | $200,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $200,000 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $510,000 | $510,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Regional Surface Transportation Program Funds (RSTP) (FHWA) | $229,930 | ||||||||||||||
Preliminary Engineering | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way (aka Land Acquisition) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Construction | $229,930 | $0 | $229,930 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | |
Grand Total | $3,632,849 | $1,480,000 | $1,267,849 | $0 | $0 | $685,000 | $0 | $0 | $200,000 | $0 | $0 | $0 | $0 | $0 |
Miles of Trails Developed or Improved | None | 1 | miles |
Miles of Pedestrian and Bicycle Routes Improved or Constructed | ||||
---|---|---|---|---|
|
2017 | Total | Units | |
Action Performed | Path or Route Type | |||
Constructed | Class I/Shared Use Path | 0.75 | 0.75 | miles |
Total | 0.75 | 0.75 | miles |
Total | |||
---|---|---|---|
AQ Mitigation Funds (TRPA) | $260,419 | $260,419 | $0 |
California Tahoe Conservancy (CTC) | $645,000 | $645,000 | $0 |
Caltrans DEMO Funds (FHWA) | $1,655,000 | $1,655,000 | $0 |
City of South Lake Tahoe General Fund (CSLT) | $1,007,430 | $1,007,430 | $0 |
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) | $710,000 | $710,000 | $0 |
Grand Total | $4,277,849 | $4,277,849 | $0 |
Total | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
AQ Mitigation Funds | $260,419 | $260,419 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
California Tahoe Conservancy | $645,000 | $0 | $0 | $0 | $0 | $0 | $0 | $35,572 | $105,160 | $62,304 | $19,475 | $422,489 |
Caltrans DEMO Funds | $1,655,000 | $970,024 | $122,903 | $274,939 | $286,067 | $1,067 | $0 | $0 | $0 | $0 | $0 | $0 |
City of South Lake Tahoe General Fund | $658,536 | $658,536 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Congestion Mitigation and Air Quality Program (CMA... | $710,000 | $510,000 | $0 | $86,883 | $14,070 | $20,030 | $34,504 | $44,513 | $0 | $0 | $0 | $0 |
Proposition 50 (Inactive) | $100,060 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $58,848 | $41,212 | $0 | $0 |
Grand Total | $4,029,015 | $2,398,979 | $122,903 | $361,822 | $300,137 | $21,097 | $34,504 | $80,085 | $164,008 | $103,516 | $19,475 | $422,489 |
No Related Projects set for this project.
No external links entered.
No notes entered.