Overview

Basics

Basics
Project is the fourth and final phase of the larger Lake Forest Watershed. This phase addressed right of way (ROW) storm water along Lake Forest Road and the Panorama neighborhood (2 miles east of Tahoe City). Project included restoration of CA State Parks channel/wetlands and wetlands restoration/ new outfall at Bristlecone. This project incorporated low impact design (LID) components with pervious pavement design, along with several filtering components and a Jellyfish filter.

Completed
2007
2014
2020
$6,700,962

Kansas McGahan (kmcgahan@placer.ca.gov)
06/01/2014
01/13/2021
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2020 Total Units
Property Ownership Road Type Treatment Type
Placer County Paved Retrofitted 2.2 2.2 miles
Total 2.2 2.2 miles
Linear Feet of Stream Channel Restored or Enhanced
2020 Total Units
Action Performed Watershed
Restored Lake Forest Creek 750 750 linear feet
Total 750 750 linear feet
Acres of SEZ Restored or Enhanced
2020 Total Units
Action Performed
Restored 1.12 1.12 acres
Total 1.12 1.12 acres
Acres of Habitat Restored or Enhanced
2020 Total Units
Action Performed Habitat Type
Restored SEZ/Wetland 1.12 1.12 acres
Total 1.12 1.12 acres
Miles of Trails Developed or Improved
2020 Total Units
Action Performed
Improved 0.25 0.25 miles
Total 0.25 0.25 miles

No accomplishments to report for:
Year(s) 2014, 2015, 2016, 2017, 2018, 2019
Explanation No accomplishments for these years

Funding

Expected Funding

Expected Funding
$6,700,962
$6,715,962
($15,000)

Total
Placer County General Fund (PLCO) $15,000 $15,000 $0
Unknown or Unassigned $6,700,962 $6,700,962 $0
Grand Total $6,715,962 $6,715,962 $0

Reported Expenditures

Reported Expenditures
Total 2020 2019 2018 2017 2016 2015 2014 2013 2012 2011 2010 2009 2008 2007
California Lahontan Regional Water Quality Control... $750,000 $0 $0 $0 $0 $0 $6,358 $743,642 $0 $0 $0 $0 $0 $0 $0
California Tahoe Conservancy $5,260,537 $0 $0 $0 $0 $0 $0 $83,478 $678,242 $72,760 $174,868 $495,130 $547,009 $394,586 $2,814,464
Placer County General Fund $98,894 $2,000 $3,000 $3,000 $15,000 $15,000 $36,614 $0 $0 $0 $0 $24,280 $0 $0 $0
Regional Surface Transportation Program Funds (RST... $26,879 $0 $0 $0 $0 $0 $5,289 $15,098 $2,591 $3,299 $602 $0 $0 $0 $0
SEZ Mitigation Funds $47,920 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $47,920
Southern Nevada Public Land Management Act $5,408,690 $0 $0 $0 $0 $0 $133,844 $3,174,080 $83,389 $281,068 $278,932 $389,052 $51,251 $882,035 $135,039
U.S. Army Corps of Engineers $2,075,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,475,892 $599,108 $0 $0
U.S. Bureau of Reclamation $750,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000 $184,951 $315,049 $0
WQ Mitigation Funds $26,879 $0 $0 $0 $0 $0 $5,289 $15,098 $2,591 $3,299 $602 $0 $0 $0 $0
Grand Total $14,444,799 $2,000 $3,000 $3,000 $15,000 $15,000 $187,394 $4,031,396 $766,813 $360,426 $455,004 $2,634,354 $1,382,319 $1,591,670 $2,997,423

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
01/06/2020 1:56 PM Kansas McGahan Project is complete; however, Placer County continues to monitor the restoration with annual CRAM assessments.
01/14/2019 3:30 PM Beth Vollmer The project is completed, however, Lahontan required five years of post-project monitoring which we are currently doing..
08/04/2015 2:38 PM Jeanne McNamara Note that SEZ restoration for this project was previously reported in 2010 before construction began and the restoration did not occur until 2014.